Sentinel Audit II:  Status of the Federal Bureau of Investigation’s Case Management System (Redacted)

Audit Report 07-03
December 2006
Office of the Inspector General


Appendix 8
The Federal Bureau of Investigation’s
Response to the Draft Report


  U.S. Department of Justice
Federal Bureau of Investigation
Washington, D. C. 20535-0001

November 7, 2006




The Honorable Glenn A. Fine
Inspector General
Office of the Inspector General
U.S. Department of Justice
Room 4322
950 Pennsylvania Avenue, N.W.
Washington, D.C. 20530

Re:   WORKING DRAFT "AUDIT REPORT--SENTINEL AUDIT II: STATUS OF THE FEDERAL BUREAU OF INVESTIGATION'S CASE MANAGEMENT SYSTEM

Dear Mr. Fine:

The Federal Bureau of Investigation (FBI) appreciates your efforts, and those of your staff, in assessing the progress of our SENTINEL Program. As always, the FBI welcomes your observations and final recommendations.

We have completed our review of your draft report entitled "SENTINEL Audit II:  Status of the Federal Bureau of Investigation's Case Management System." Enclosed is the FBI's response to your preliminary findings and recommendations. The response has undergone a classification review and sensitivity review and is enclosed with this letter.

Please contact either me, on 202-324-2307, or Mr. Mio Lazarevich, SENTINEL Program Manager, should you have any questions. Mr. Lazarevich may be reached on 703-983-9610.

Sincerely,

[signed]

Dean E. Hall
Project Management Executive

Enclosures

 

FBI Response to the DOJ/OIG Draft Audit Report
SENTINEL Audit II:  Status of the Federal Bureau of Investigation’s
Case Management System


Recommendation # 1:  Ensure the management reserve is based on an assessment of project risks for each phase and for the project overall.

FBI Response:   Agree. The FBI’s Deputy Director governs the use of the management reserve through the Finance Division (FD). The SENTINEL Program Management Office (PMO) will work with FD and senior FBI management to determine the appropriate management reserve for each phase. The PMO asserts that 11 percent is an appropriate overall reserve amount and may be adjusted per phase depending on a comprehensive assessment of risk.

Recommendation # 2:  Periodically update the estimate of total project costs as actual cost data is available.

FBI Response:   Agree. Since contract award, the PMO, in conjunction with Lockheed Martin (Lockheed) and FD, has worked to revise projected program costs as appropriate, and will continue to do so over the life of the project. These changes will be communicated through budget requests and the OMB Exhibit 300 process.

Recommendation # 3:  Complete contingency plans as required by the SENTINEL Risk Management Plan.

FBI Response:   Agree. During the course of this audit, the Office of IT Policy and Planning (OIPP) released Version 2 of the FBI’s Risk Management Plan. The most recent version only requires “contingency triggers” and plans for high risks. The SENTINEL Risk Management Plan is being revised so that it complies with the new OIPP risk policy. That being said, the first high risk was identified in mid-October. This risk was associated with schedule compression. The PMO is evaluating Lockheed’s re-plan strategy and is developing contingency plans for this high risk.

Recommendation # 4:  Ensure that the independent verification and validation process is conducted through project completion.

FBI Response:   Agree. The FBI, as stated in the audit, will be providing experienced contractors to perform this service. Along those lines, the Independent Verification and Validation (IV&V) services will report to the CIO on both the PMO and Lockheed’s performance as mandated by the program plan.

Recommendation # 5:  Complete hiring as soon as possible for the vacant PMO positions needed during the current project phase.

FBI Response:   Agree. The PMO continues to aggressively fill government and contractor positions. The two vacancies represent less than 5 percent of the total PMO staffing. The PMO believes that this is significantly less than government and industry levels, and will continue to actively recruit for positions before vacancies occur. Since the PMO requires contractors to have existing security clearances, contractor replacements have tended to be very quick, generally less than 30 days. The six O&M vacancies that had been deferred are currently being finalized for recruitment.



« Previous Table of Contents Next »