No. 97-1897
In the Supreme Court of the United States
OCTOBER TERM, 1997
VISTA PAINT CORPORATION, PETITIONER
v.
UNITED STATES OF AMERICA
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
BRIEF FOR THE UNITED STATES IN OPPOSITION
SETH P. WAXMAN
Solicitor General
Counsel of Record
PETER S. COPPELMAN
Acting Assistant Attorney
General
GREER S. GOLDMAN
MARTIN W. MATZEN
Attorneys
Department of Justice
Washington, D.C. 20530-0001
(202) 514-2217
QUESTIONS PRESENTED
1. Whether a defendant in a civil enforcement action under the Clean Air
Act (42 U.S.C. 7401 et seq.) is barred from asserting as an affirmative
defense that the standards contained in a State Implementation Plan approved
by the Environmental Protection Agency are technologically or economically
infeasible.
2. Whether the district court acted within its discretion in declining to
impose the burden of proof on either party in assessing a civil penalty
against petitioner for violations of the Clean Air Act (42 U.S.C. 7401 et
seq.).
3. Whether the district court acted within its discretion by ordering the
parties to submit their trial witnesses' direct testimony by affidavit and
to make the witnesses available for cross-examination.
In the Supreme Court of the United States
OCTOBER TERM, 1997
No. 97-1897
VISTA PAINT CORPORATION, PETITIONER
v.
UNITED STATES OF AMERICA
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
BRIEF FOR THE UNITED STATES IN OPPOSITION
OPINIONS BELOW
The order of the court of appeals (Pet. App. 1a-2a) affirming the judgment
of the district court is unpublished, but the decision is noted at 129 F.3d
129 (1997) (Table). The district court's opinion (Pet. App. 4a-33a) setting
civil penalties is unreported. An earlier opinion of the court of appeals
(Pet. App. 34a-45a) concerning, inter alia, the district court's dismissal
of petitioner's affirmative defenses is unpublished, but the decision is
noted at 976 F.2d 739 (Table). The district court's order (Pet. App. 89a-92a)
concerning petitioner's affirmative defenses is unreported.
JURISDICTION
The judgment of the court of appeals was entered on November 4, 1997. A
petition for rehearing was denied on January 23, 1998. Pet. App. 3a. Justice
O'Connor granted petitioner an extension of time to and including May 23,
1998, to file its petition for a writ of certiorari. The petition was filed
on May 26, 1998 (a Tuesday after a federal holiday). The jurisdiction of
this Court is invoked under 28 U.S.C. 1254(1).
STATEMENT
The United States brought this action under the Clean Air Act, 42 U.S.C.
7401 et seq., to enforce provisions of California's State Implementation
Plan (SIP) limiting the levels of volatile organic compounds (VOCs) in certain
paints. VOCs are a principal source of ozone in the atmosphere. The VOC
limits were approved by the federal Environmental Protection Agency (EPA)
in 1985 as part of the California SIP. Petitioner Vista Paint Corporation,
a paint manufacturer and retailer, was still violating the VOC limits in
1987. This civil enforcement action seeks the imposition of monetary penalties
for petitioner's continued violation of the VOC limits and for petitioner's
related non-compliance with an EPA information request.
1. The Clean Air Act, as amended, requires the EPA to promulgate National
Ambient Air Quality Standards (NAAQS) for various air pollutants. 42 U.S.C.
7409. It also requires each State to submit to the EPA a plan to implement,
maintain, and enforce those standards. 42 U.S.C. 7410(a)(1). The EPA is
required to approve any such SIP that comports with the Clean Air Act. 42
U.S.C. 7410(k)(3). Once the EPA approves a SIP or SIP revision, the EPA
may enforce its provisions as federal law. 42 U.S.C. 7413(a)(1). See Train
v. Natural Resources Defense Council, 421 U.S. 60, 63-67 (1975); Union Elec.
Co. v. EPA, 427 U.S. 246, 265-266 (1976).1
Section 307(b)(1) of the Clean Air Act provides for judicial review of certain
actions by the EPA, including its promulgation of any NAAQS and its approval
of any SIP or SIP revision. 42 U.S.C. 7607(b)(1). The petition for review
must be filed in the court of appeals within 60 days after the date on which
notice of the EPA's action appeared in the Federal Register. Ibid. The Act
further provides that any "[a]ction of the [EPA] Administrator with
respect to which review could have been obtained under [Section 307(b)(1)]
shall not be subject to judicial review in civil or criminal proceedings
for enforcement." 42 U.S.C. 7607(b)(2).
The EPA has the authority to require any person subject to the Clean Air
Act to establish and maintain records and to provide such information as
the EPA may reasonably require to determine whether a violation of the Act
has occurred. 42 U.S.C. 7414(a)(1) (A), (B) and (G).
A person who violates a SIP or refuses to comply with an information request
is liable for a civil penalty of up to $25,000 for each day of violation.
42 U.S.C. 7413(b).
2. The State of California delegates primary responsibility for air pollution
control to local and regional authorities. In 1984, two such authorities,
the South Coast Air Quality Management District and the San Diego County
Air Pollution Control District, adopted rules governing the VOC content
of non-flat architectural coatings, which are more commonly known as gloss
and semi-gloss paint. The rules specify that each liter of such paint may
contain no more than 250 grams of VOC. The EPA approved those rules as part
of the California SIP on January 24, 1985. 50 Fed. Reg. 3338 (1995).2
3. On June 12, 1987, petitioner admitted to the EPA that it was still selling
paint that violated the VOC limits in the California SIP. The EPA, pursuant
to Section 113(a)(1) of the Clean Air Act, 42 U.S.C. 7413(a)(1), issued
a Notice of Violation to petitioner. The EPA also sent information requests
to petitioner, pursuant to Section 114 of the Clean Air Act, 42 U.S.C. 7414,
seeking documentation of the quantity, sales volume, and VOC content of
all non-compliant paint that petitioner manufactured and sold from July
to October 1987. The EPA warned petitioner of the $25,000 per day penalty
for not providing the information in a timely manner. Pet. App. 8a-9a.
Petitioner continued to manufacture non-compliant paints until June 1987
and continued to sell non-compliant paints until October 1987. But petitioner
did not file the reports required by the EPA that would have reflected those
sales. Pet. App. 9a, 15a-16a.
4. In 1990, the United States, at the request of the EPA, brought this enforcement
action against petitioner under the Clean Air Act. Pet. App. 73a-79a. The
government contended that petitioner had failed to comply with the VOC limits,
in violation of 42 U.S.C. 7410, and had failed to comply with an EPA information
request, in violation of 42 U.S.C. 7414. Ibid.
Petitioner asserted various affirmative defenses and counterclaims alleging
that the VOC limits were invalid under federal and state law.3 The district
court dismissed all of petitioner's so-called "invalidity" defenses
and counterclaims. Pet. App. 91a-92a.
The district court subsequently granted the government's motion for summary
judgment, concluding that petitioner had violated the Clean Air Act by failing
to comply with the VOC limits and with the EPA's information request. Pet.
App. 69a-72a. The court imposed civil penalties totalling more than $3 million.
Id. at 19a.
5. The Ninth Circuit affirmed in part and reversed in part. Pet. App. 34a-45a.
The court held that the district court had properly dismissed petitioner's
affirmative defenses and counterclaims contesting the validity of the VOC
limits, explaining that petitioner had "ample opportunity" to
"challenge EPA's approval of the inclusion of those rules in the SIP
pursuant to section 307(b)(1) of the [Clean Air Act]," 42 U.S.C. 7607(b)(1).
Pet. App. 36a. The court also held that the district court had properly
granted summary judgment on petitioner's liability under the Clean Air Act
for selling and offering for sale non-compliant paint and for failing to
comply with the EPA's information request. Id. at 37a-38a.
The court of appeals held that summary judgment should not have been granted,
however, with respect to the amount of petitioner's civil penalty. Pet.
App. 45a. The court remanded the case for trial on various disputed factual
issues relating to the appropriate amount of the penalty. Those issues included
the economic impact of the penalty on petitioner's business, whether petitioner
had made good faith efforts to comply with the VOC limits, the seriousness
of petitioner's violations, and whether the penalty should be reduced as
a result of the EPA's inaction on the proposed revisions to the VOC limits
sub- mitted by the two regional pollution-control dis- tricts (see note
2, supra). Id. at 39a-43a; see 42 U.S.C. 7413(e)(1) (non-exclusive list
of factors to be considered by courts in imposing penalties under Clean
Air Act).4
This Court denied certiorari. 510 U.S. 826 (1993).
6. On remand, the district court held that neither party would bear the
burden of proof at the bench trial on issues relating to the amount of the
penalty. Pet. App. 87a. The court explained that the determination of an
appropriate penalty involved the "weighing and balancing [of] the proper
statutory factors and common law factors against the facts which [the court]
finds from all the evidence admitted at trial." Ibid. The court directed
the parties to submit the trial testimony of all direct witnesses by affidavit
and to make those witnesses available during trial for cross-examination.
Id. at 80a-81a.
In April 1996, the district court entered findings of fact and conclusions
of law, which determined that petitioner should be assessed a civil penalty
of $1,111,250-$559,000 for petitioner's continued sale of non-compliant
paint, in violation of 42 U.S.C. 7410, and $552,250 for petitioner's failure
to respond to the EPA's information request, in violation of 42 U.S.C. 7414.
Pet. App. 4a-33a. The district court separately addressed each of the penalty
factors on which the court of appeals had ordered a trial. Id. at 24a-32a.
First, the district court concluded that petitioner, as "an expanding
business with increasing annual gross sales revenues in the range of 45
to 47 million dollars annually," was fully capable of paying the $1,111,250
penalty. Pet. App. 25a. The court concluded that a penalty of that size
would neither "undermine [petitioner's] financial structure" nor
"place [petitioner] in jeopardy of 'going-out-of-business.'" Ibid.
Second, as for whether petitioner had made good faith efforts to comply
with the Clean Air Act, the district court concluded that petitioner had
"knowingly and intentionally violated federal law from at least December
3, 1985, to October 12, 1987" by continuing to sell non-compliant paints,
"ignoring during that period repeated warnings by EPA and the June
1987 Notice of Violation." Pet. App. 26a. The court also found that
petitioner had made "no real good faith effort" to respond to
the EPA's information request. Ibid. The court observed that petitioner's
"corporate state of mind was to engage in a pattern of continued non-cooperation
with [EPA's] enforcement efforts by withholding the documentation of its
violations or by providing incomplete information regarding such while it
continued to sell and offer to sell non-compliant coatings." Id. at
27a.
Third, the district court held that petitioner's violations of the VOC limits
were sufficiently serious to warrant a "moderate penalty." Pet.
App. 28a. The court explained that "a major reduction in atmospheric
pollutants" would have occurred in the affected regions if petitioner
had promptly complied with the VOC limits. Id. at 27a. But the court declined
to find that petitioner's failure to do so had a "measurable negative
impact on human health and the environment." Id. at 28a. The court
also concluded that petitioner's failure to comply with EPA's information
request warranted a "moderate to substantial penalty," because
the effectiveness of the EPA's enforcement of the Clean Air Act depends
in large part on the provision of information from regulated industries
such as petitioner. Ibid.
Fourth, the district court held that EPA had not engaged in unreasonable
delay in reviewing the proposed modifications of the VOC limits submitted
by the regional pollution-control districts. Pet. App. 28a-29a. "In
any event," the court added, "even if there were unreasonable
delays in acting on the proposed rule revisions, Vista was not prejudiced
by them because Vista violated federal law before and after the rule revisions
were submitted to EPA." Id. at 29a. The court did, however, conclude
that the government should have filed suit against petitioner more promptly
for non-compliance with the EPA's information request. Id. at 30a-31a. The
court held that "[s]uch delay supports a moderate reduction in penalty
for the period June 21, 1989 to January 18, 1991." Id. at 31a.
Finally, as for the statutory penalty factors on which the court of appeals
had found no dispute of fact, the district court observed that three of
those factors supported a "substantial penalty." Pet. App. 31a-32a.
The court stated that petitioner had "a history of non-full compliance,"
as demonstrated by "the extent and degree" of the violations at
issue; that petitioner's violations were of an extended duration, "spann[ing]
a period of almost six years"; and that petitioner had "obtained
significant economic benefit" from its violations. Ibid. As for the
final factor, whether petitioner had previously paid penalties for the same
violations, the court found that petitioner's prior payments totaled only
$500. Ibid.
7. The Ninth Circuit affirmed in an unpublished order "for the reasons
stated in the district court's Findings of Fact and Conclusions of Law."
Pet. App. 2a.
ARGUMENT
The court of appeals' unpublished decisions in this case are correct and
do not conflict with any decision of this Court or any other court of appeals.
This Court's review is therefore not warranted.
1. a. Petitioner principally contends (Pet. 8) that the court of appeals
erred in its initial decision in this case by holding that a defendant in
a civil enforcement proceeding under the Clean Air Act cannot assert as
a defense to liability that compliance with a SIP is "economic[ally]
or technological[ly] infeasib[le]." But the court of appeals did not
so hold. Nor did petitioner ask the court of appeals to rule on whether
such a defense is cognizable in a civil enforcement proceeding. This Court
does not grant certiorari to "decide questions not raised or resolved
in the lower courts." Taylor v. Freeland & Kronz, 503 U.S. 638,
646 (1992).
Petitioner, in its answer to the government's complaint, asserted as defenses
to liability that the VOC limits in the California SIP were invalid as contrary
to federal and state law, including the California Health and Safety Code.5
Petitioner's invalidity defenses did not, however, refer to infeasibility
in any way, much less cite the specific sections of the California Health
and Safety Code on which petitioner now relies. The invalidity defenses
thus did not fairly raise any issue of technological or economic feasibility.
And petitioner did not suggest to the court of appeals in its briefs that
the invalidity defenses were predicated on the technological or economic
infeasibility of the VOC limits.6 There is thus no reason to suppose that
the Ninth Circuit's single-sentence holding that "the district court
lacked subject matter jurisdiction over * * * the affirmative defenses dealing
with invalidity" (Pet. App. 36a) was directed at defenses based on
technological or economic infeasibility.
Similarly, in its earlier petition for a writ of certiorari in this case
challenging the dismissal of the invalidity defenses, petitioner did not
contend that those defenses involved feasibility issues. See Pet. 10-11,
18-20, Vista Paint Corp. v. United States, No. 92-2026 (9th Cir.) (discussing
invalidity defenses). And, in refuting petitioner's assertion of a circuit
conflict as to which defenses may be raised in a civil enforcement proceeding
under the Clean Air Act, the United States explained that the allegedly
conflicting cases involved "claims of economic or technological infeasibility,"
whereas "the claim in this case is not one of technological or economic
infeasibility, but rather of the invalidity of the VOC regulations under
state law." U.S. Supp. Br. 13-14, Vista Paint Corp. v. United States,
No. 92-2026. Petitioner did not take issue at that time with the government's
characterization of its invalidity defenses as not being based on technological
or economic feasibility. The petition for certiorari was denied. 510 U.S.
826 (1993).
b. The only issue fairly raised by petitioner's invalidity defenses, therefore,
is whether the VOC limits were promulgated in accordance with the requirements
of state law (e.g., any requirement that an environmental impact report
be prepared, see note 6, supra).7 The court of appeals' decision that such
defenses cannot be asserted in a civil enforcement proceeding under the
Clean Air Act is correct and consistent with the decisions of other circuits.
Section 307(b)(1) of the Clean Air Act, 42 U.S.C. 7607(b)(1), authorizes
judicial review in the courts of appeals of certain actions by the EPA,
including its approval of a SIP, and requires that any petition for review
be filed within 60 days after notice of the EPA's action appears in the
Federal Register. Section 307(b)(2), 42 U.S.C. 7607(b)(2), then provides
that any "[a]ction of the [EPA] Administrator with respect to which
review could have been obtained under [Section 307(b)(1)] shall not be subject
to judicial review in civil or criminal proceedings for enforcement."
This Court has recognized that Section 307(b)(2) bars a defendant in a criminal
enforcement proceeding for violation of a regulation promulgated under the
Clean Air Act from raising various challenges to the validity of that regulation,
including "whether the [EPA] Administrator has complied with appropriate
procedures in promulgating the regulation in question, or whether the particular
regulation is arbitrary, capricious, or supported by the administrative
record." Adamo Wrecking Co. v. United States, 434 U.S. 275, 285 (1978).
And the courts of appeals have uniformly held that Section 307(b)(2) bars
a party from challenging the validity of an EPA action in a civil enforcement
proceeding-or any other sort of proceeding-on any ground that could have
been considered by the EPA in deciding whether to take the action in the
first place and by the court of appeals in reviewing the EPA's action under
Section 307(b) (1). See, e.g., United States v. Ford Motor Co., 814 F.2d
1099, 1103 (6th Cir.), cert. denied, 484 U.S. 822 (1987); United States
v. Ethyl Corp., 761 F.2d 1153, 1155-1157 (5th Cir. 1985), cert. denied,
474 U.S. 1070 (1986); Action for Rational Transit v. West Side Highway Project,
699 F.2d 614, 616 (2d Cir. 1983); cf. Lubrizol Corp. v. EPA, 562 F.2d 807,
813-815 (D.C. Cir. 1977).8
The Ninth Circuit's decision that the district court lacked jurisdiction
over petitioner's invalidity defenses is consistent with those decisions.
In determining whether to approve the California SIP, the EPA could have
considered petitioner's arguments that the VOC limits were promulgated in
violation of state law, because States must provide the EPA with assurances
that they have the authority under state law to carry out a SIP. 42 U.S.C.
7410(a) (2)(E). And the court of appeals could then have considered that
issue on a petition for review under Section 307(b)(1) challenging the EPA's
approval of the California SIP. Accordingly, because petitioner could have
raised its claim that the VOC limits are contrary to state law on a petition
for review under Section 307(b)(1), the district court was without jurisdiction
to consider such a claim in a civil enforcement proceeding.9
c. Petitioner also argues (Pet. 12-14) that defendants in civil enforcement
proceedings under the Clean Air Act cannot constitutionally be precluded
from challenging the validity of a SIP requirement. But no such constitutional
challenge to Section 307(b)(2) was presented to or addressed by the courts
below. Nor has petitioner identified any decision of any court holding Section
307(b)(2) (or any similar statutory provision) to be unconstitutional. See
generally Yakus v. United States, 321 U.S. 414 (1944) (upholding constitutionality
of statute precluding challenges to validity of price controls in enforcement
proceedings); Lloyd A. Fry Roofing Co. v. EPA, 554 F.2d 885, 892-893 (8th
Cir. 1977) (rejecting argument that precluding challenges to validity of
EPA regulations outside time period allowed by Section 307(b)(1) violates
due process).
Moreover, to the extent that petitioner's challenge to the VOC limits was
actually based (as petitioner now contends) on issues of technological and
economic feasibility, petitioner was free to raise such issues during the
penalty phase of the case in an effort to show "good faith efforts
to comply" with the VOC limits. See 42 U.S.C. 7413(e)(1) (listing penalty
factors); see also Ford Motor Co., 814 F.2d at 1104 ("technical infeasibility
coupled with good faith efforts can be considered by the district court
as a factor mitigating against the imposition of monetary penalties in the
enforcement action"). The Ninth Circuit's initial opinion in this case
addressed only the defenses that petitioner could raise to liability. That
ruling had no legal or practical effect on petitioner's ability to attempt
to persuade the district court on remand that little or no penalty should
be imposed because its compliance with the SIP was technologically or economically
infeasible. And neither the district court nor the Ninth Circuit subsequently
held that feasibility issues could not be considered in mitigation of any
penalty.
2. Petitioner next urges (Pet. 17) the Court to resolve a "conflict
of authority" as to the allocation of the burden of proof on the various
factors that Section 113(e)(1) of the Clean Air Act, 42 U.S.C. 7413(e)(1),
directs the district courts to consider in determining the amount of a penalty.
But no such conflict exists.
In this case, the district court held (Pet. App. 87a), and the court of
appeals agreed (id. at 2a), that neither party bore the burden of proof
on the Section 113(e)(1) penalty factors.10 Instead, the district court
concluded (id. at 87a) that it should "receive[] admissible evidence
from both sides," "weigh[] and balanc[e] the proper statutory
and common law factors against the facts which it finds from all the evidence
admitted at trial," and then "exercise[] its discretion in determining
the amount, if any, of the penalty." Cf. Tull v. United States, 481
U.S. 412, 427 (1987) (recognizing that district courts must engage in "highly
discretionary calculations that take into account multiple factors"
in setting civil penalties under the Clean Water Act).
Petitioner has identified no decision that adopts a position contrary to
that of the courts below on the allocation of the burden of proof under
Section 113(e)(1). None of the appellate decisions cited by petitioner even
addresses the burden of proof. Petitioner does cite two district court decisions
that declined to require a defendant to bear the burden of proving that
its penalty should be less than the statutory maximum.11 But those decisions
are entirely consistent with the decision in this case, which likewise held
that petitioner did not bear the burden of proof on the amount of its penalty.12
In short, petitioner has offered no authority under Section 113(e)(1) of
the Clean Air Act, or any parallel provision of any other environmental
statute, adopting its view that the courts below should have "place[d]
squarely on the Government the burden of proving the facts underlying the
penalty factors" (Pet. 17).
Petitioner also seizes on the district court's statement that "[t]his
Court will first determine the maximum penalty allowable and then consider
any mitigating circumstances" (Pet. App. 22a), asserting that the district
court thereby "presumptively appl[ied] the maximum penalty and require[d]
[petitioner] to prove facts in mitigation" (Pet. 16). But petitioner
is reading more into the district court's statement than its words or their
context can bear. It is evident from the entirety of the district court's
opinion, and from its holding, that no presumption was made that the statutory
maximum penalty should apply. The court found that most of the Section 113(e)(1)
factors favored a "substantial" penalty. See Pet. App. 25a-28a,
31a-32a. Yet, the court imposed penalties ranging from $250 to $2500 per
day of violation- i.e., from one percent to ten percent of the statutory
maximum of $25,000 per day of violation. Id. at 39a; 42 U.S.C. 7413(d)(1).
Nor would the district court's statement, even if read in the manner that
petitioner suggests, create a conflict among the circuits. The courts of
appeals are in agreement that "[i]n considering fines under the Act,
courts generally presume that the maximum penalty should be imposed."
United States v. B & W Inv. Properties, 38 F.3d 362, 368 (7th Cir. 1994),
cert. denied, 514 U.S. 1126 (1995); accord United States v. Marine Shale
Processors, 81 F.3d 1329, 1337 (5th Cir. 1996) ("when imposing penalties
under the environmental laws, courts often begin by calculating the maximum
possible penalty, then reducing the penalty only if mitigating circumstances
are found to exist"); Atlantic States Legal Found., Inc. v. Tyson Foods,
Inc., 897 F.2d 1128, 1137 (11th Cir. 1990). None of the district court decisions
that petitioner cites as conflicting holds that such an approach is impermissible.13
And one of those decisions itself adopts such an approach. See United States
v. Midwest Suspension & Brake, 824 F. Supp. 713, 735 (E.D. Mich. 1993)
("in calculating the amount of civil penalties to be imposed on defendant
[under the Clean Air Act], this Court must start with the statutory maximum
and make any downward adjustments based on the evidence adduced at trial"),
aff'd, 49 F.3d 1197 (6th Cir. 1995).
In any event, even if one assumes arguendo that the lower courts erred in
not requiring the government to bear the burden of proof on all of the Section
113(e)(1) penalty factors, petitioner has not even attempted to demonstrate
that any such error was prejudicial in this case. The burden of proof is
dispositive in a civil case only in those relatively rare circumstances
where the parties' evidence is in equipoise. Cf. Medina v. California, 505
U.S. 437, 449 (1992). Nothing in the district court's decision suggests
that the evidence was in equipoise on any of the Section 113(e)(1) penalty
factors. It thus appears that the district court would have reached the
same conclusion on the amount of petitioner's penalty regardless of whether
the burden of proof was placed on the government, on petitioner, or on neither
party.
3. Finally, petitioner complains (Pet. 15-20) that the district court abused
its discretion in its conduct of the trial on the Section 113(e)(1) penalty
factors, because the court required the parties to submit the testimony
of their direct witnesses by affidavit rather than in person. The court
also required, however, that those witnesses be made available at trial
for cross-examination. See Pet. App. 80a-81a. As the courts of appeals have
recognized, "[a] district court's requirement that parties submit direct
evidence in written form, while permitting parties to cross-examine adverse
witnesses orally," is "an accepted and encouraged technique for
shortening bench trials." Ball v. Interoceanica Corp., 71 F.3d 73,
77 (2d Cir. 1995) (quoting Phonetele Inc. v. American Tel. & Tel. Co.,
889 F.2d 224, 232 (9th Cir. 1989), cert. denied, 503 U.S. 914 (1992)); see
also Eirhart v. Libbey-Owens-Ford Co., 996 F.2d 837, 840 (7th Cir. 1993)
(district courts may conduct bench trials on "a written record").
Petitioner nonetheless contends (Pet. 17-20) that such a procedure is inconsistent
with Rule 43(a) of the Federal Rules of Civil Procedure, which provides
that "[i]n every trial, the testimony of witnesses shall be taken in
open court, unless a federal law, these rules, the Federal Rules of Evidence,
or other rules adopted by the Supreme Court provide otherwise." Rule
43(a), by its terms, thus gives way in the face of inconsistency with, inter
alia, the Federal Rules of Evidence. The courts have construed Federal Rule
of Evidence 611(a), which gives trial courts broad authority over "the
mode and order of interrogating witnesses" in order to "avoid
needless consumption of time," as permitting the introduction of direct
testimony in the form of affidavits at bench trials. See, e.g., In re Adair,
965 F.2d 777, 779-780 (9th Cir. 1992); Saverson v. Levitt, 162 F.R.D. 407,
408-409 (D.D.C. 1995).
Petitioner claims (Pet. 19-20) that several cases are in conflict with Adair,
Ball, and the decision below. But there is no true circuit conflict. None
of the appellate cases relied on by petitioner concerned a district court's
order that the parties submit their witnesses' direct evidence by affidavit
at a bench trial while making the witnesses available in person for cross-examination.
Two of those cases reversed a district court's grant of summary judgment,
based on affidavits or other evidence, where various genuine disputes of
material fact appeared to exist. See Ross v. Franzen, 777 F.2d 1216, 1220-1221
(7th Cir. 1985); United States v. J.B. Williams Co., 498 F.2d 414, 430-434
(2d Cir. 1974).14 Those cases are obviously not on point. Both the Second
Circuit and the Seventh Circuit have since approved of trial procedures
similar to those used in this case. See Ball, 71 F.3d at 76; Eirhart, 996
F.2d at 840.
A third case held that a district court could not conduct the trial of a
prisoner's civil-rights suit "solely on affidavits," especially
in circumstances where the prisoner was entitled to a trial by jury. See
Dolence v. Flynn, 628 F.2d 1280, 1281-1282 (10th Cir. 1980). Dolence is
distinguishable from the present case in at least two respects. The trial
of this case was not conducted "solely on affidavits," because
the witnesses were subject to live cross-examination. And the issues in
this case were triable to the court rather than to a jury. A district court
is allowed more latitude over the manner in which evidence will be introduced
at a bench trial as opposed to a jury trial. See, e.g., Southern Pacific
Transp. Co. v. Chabert, 973 F.2d 441, 448 (5th Cir. 1992), cert. denied,
507 U.S. 987 (1993). Similar reasons distinguish the present case from Lebeck
v. William A. Jarvis, Inc., 250 F.2d 285, 294-295 (3d Cir. 1957), which
held that a district court should not have read an edited transcript of
a witness's testimony to the jury, but instead should have required the
witness to testify in person.
The case most analogous to this one is Walton v. United Consumers Club,
Inc., 786 F.2d 303, 312-313 (7th Cir. 1986), which concluded that a district
court should not have admitted the plaintiffs' interrogatory answers at
a bench trial in lieu of live testimony, even though the plaintiffs were
subject to cross-examination about those answers. But the court of appeals
in that case did not consider the relationship between Rule 43(a) of the
Federal Rules of Civil Procedure and Rule 611(a) of the Federal Rules of
Evidence. And, in any event, the court of appeals ultimately held that the
admission of the affidavits was harmless and consequently did not require
reversal. 786 F.2d at 313. There is thus no tension in the outcomes of Walton
and the present case. Petitioner has not even attempted to demonstrate any
prejudice resulting from the district court's mode of obtaining witnesses'
testimony.
CONCLUSION
The petition for a writ of certiorari should be denied.
Respectfully submitted.
SETH P. WAXMAN
Solicitor General
PETER S. COPPELMAN
Acting Assistant Attorney
General
GREER S. GOLDMAN
MARTIN W. MATZEN
Attorneys
AUGUST 1998
1 Under the Clean Air Act, the States retain the authority to adopt their
own air pollution control standards and limitations, as long as those standards
and limitations are no less stringent than those imposed by federal law.
42 U.S.C. 7416; see Union Elec., 427 U.S. at 265.
2 Both districts later adopted more lenient versions of those rules and
submitted them to the EPA for approval. But the EPA did not approve them.
The revised rules therefore have no effect on the enforceability of the
VOC limits approved by the EPA in 1985 as part of the California SIP. 42
U.S.C. 7416; General Motors Corp. v. United States, 496 U.S. 530, 540 (1990).
3 Petitioner contended that the VOC limits were void as contrary to the
California Health and Safety Code, the California Environmental Quality
Act, and the state and federal constitutions. See Vista C.A. Br. 17-18,
United States v. Vista Paint Corp., No. 92-55160 (9th Cir.).
4 Section 113(e)(1) of the Clean Air Act, 42 U.S.C. 7413(e)(1), provides,
in pertinent part, that
the court * * * shall take into consideration (in addition to such other
factors as justice may require) the size of the business, the economic impact
of the penalty on the business, the violator's full compliance history and
good faith efforts to comply, the duration of the violation as established
by any credible evidence * * * , payment by the violator of penalties previously
assessed for the same violation, the economic benefit of noncompliance,
and the seriousness of the violation.
5 Petitioner asserted six defenses arguing that the VOC limits were invalid.
The first and second invalidity defenses contended that the local pollution-control
agencies, in promulgating the VOC limits, "violated the provisions
of the California Health and Safety Code relating to rulemaking, the provisions
of the California Public Resources Code relating to environmental impact
analysis, and the Contract Clauses, the Due Process Clauses, the Takings
Clauses, and the Delegation Doctrine under the California and United States
Constitutions." Vista Answer ¶¶ 22-25. The third and fourth
invalidity defenses contended that the California Air Resources Board, in
incorporating the VOC limits into the California SIP, "violated the
provisions of the California Health and Safety Code relating to approval
or disapproval of local rules as plan portions, the provisions of the California
Public Resources Code relating to environmental analysis, and the Contract
Clauses, the Due Process Clauses, the Takings Clauses, and the Delegation
Doctrine under the California and United States Constitutions." Id.
¶¶ 26-29. The fifth and sixth invalidity defenses asserted that
the EPA, in approving the VOC limits as part of the California SIP, "violated
the provisions of the [Clean Air] Act relating to federal approval or disapproval
of state plans, the provisions of the National Environmental Policy Act
relating to environmental impact analyses, relevant portions of the Administrative
Procedure Act and other applicable laws governing the decision-making of
federal administrative agencies, and the Due Process and Takings Clauses
of the Fifth Amendment and the Delegation Doctrine under the United States
Constitution." Id. ¶¶ 30-33.
6 Petitioner informed the court of appeals that its "affirmative defenses
alleged that both 1984 [VOC] rules had 'violated' the [California Health
and Safety] Code, the California Environmental Quality Act ('CEQA'), and
the state and federal constitutions and were, therefore, 'void ab initio.'"
Pet. C.A. Br. 17, United States v. Vista Paint Corp., No. 92-55160 (9th
Cir.). In elaborating on those defenses (id. at 28-30), petitioner contended
that the local pollution-control agencies (1) did not prepare environmental
impact reports with respect to the VOC limits, as required by the CEQA,
(2) did not "assess and duly consider the economic impacts [of the
VOC limits], as required by law," (3) did not have statutory rulemaking
authority over paints sold as consumer products, (4) did not comply with
state law requirements that such rules reflect "best available technological
and administrative practices," apply "reasonably available"
control measures, and be "necessary and proper" (quoting Cal.
Health & Safety Code §§ 40440(a), 40462, 40702) (West 1996));
(5) violated the due process clauses of the federal and state constitutions
by basing the VOC rules on "crystal-ball gazing" (quoting International
Harvester Co. v. Ruckelshaus, 478 F.2d 615, 623 (D.C. Cir. 1973)); (6) violated
the contract clauses of the federal and state constitutions by "severely
impair[ing] Vista's contract rights" for no "important public
purpose," and (7) did not comply with the state Administrative Procedure
Act.
7 Petitioner appears to have abandoned the portions of its invalidity defenses
arguing that the EPA's approval of the VOC limits violated various federal
constitutional and statutory provisions. See Pet. 6 (describing affirmative
defenses as asserting that "the VOC standards contained in the federally
approved SIP were invalid because they had been promulgated in violation
of California law"); Pet. 9 (noting that "Vista argued below that
the VOC standards * * * are invalid on several grounds under California
law").
8 Several circuits agree that issues of technological and economic infeasibility
may be raised in a civil enforcement action, because those issues are not
properly considered by the EPA in evaluating a SIP. See, e.g., Union Elec.
Co. v. EPA, 593 F.2d 299, 307 (8th Cir.), cert. denied, 444 U.S. 839 (1979);
Indiana & Mich. Elec. Co. v. EPA, 509 F.2d 839, 845 (7th Cir. 1975);
Buckeye Power, Inc. v. EPA, 481 F.2d 162, 173 (6th Cir. 1973), cert. denied,
409 U.S. 1125 (1973). The Third Circuit, however, has held that a defendant
cannot raise "economic hardship" as a defense in an enforcement
action because it could have raised the issue "in a section 307 hearing."
Getty Oil Co. v. Ruckelshaus, 467 F.2d 349, 357 (3d Cir. 1972). But this
Court has recognized since Getty Oil that the EPA cannot consider such issues
in Section 307(b)(1) proceedings. See Union Elec., 427 U.S. at 265-266.
To the extent that any inconsistency ever existed between Getty Oil and
the decisions of the Sixth, Seventh, and Eighth Circuits, it was over whether
economic hardship could be raised in a Section 307(b)(1) proceeding. There
was no disagreement over the basic principle that a party is barred from
raising in a civil enforcement action any question that a court of appeals
could have considered in a Section 307(b)(1) proceeding. In any event, this
case does not implicate any conflict over when issues of economic or technological
feasibility may be raised, because, as explained above, petitioner did not
argue below that its invalidity defenses were based on such issues.
9 Petitioner could likewise have raised in a Section 307(b)(1) proceeding
its arguments that the EPA, in approving the VOC limits, violated the Clean
Air Act, the National Environmental Policy Act, the Administrative Procedure
Act, and various provisions of the United States Constitution. See Lloyd
A. Fry Roofing Co. v. EPA, 554 F.2d 885, 892 (8th Cir. 1977).
10 Because the district court held that "there is no burden of proof
on either party" with respect to the Section 113(e)(1) penalty factors
(Pet. App. 87a), petitioner was not, as it contends (Pet. 16), "saddled
with the burden of proving facts to rebut the maximum penalty requested
by the Government."
11 See United States v. Midwest Suspension & Brake, 824 F. Supp. 713,
735 n.30 (E.D. Mich. 1993), aff'd, 49 F.3d 1197 (6th Cir. 1995); Student
Public Interest Research Group of New Jersey, Inc. v. Monsanto Co., Civ.
A. No. 83-2040, 1988 WL 156691, at *16 (D.N. J. Mar. 24, 1988) (citizen
suit not involving Section 113(e)(1) penalty factors).
12 Indeed, the district court in one of those cases, in words strikingly
similar to those of the district court here, explained that "the inquiry
mandated under [42 U.S.C.] § 7413(e) is for this Court to evaluate
the penalty assessment criteria in light of all of the evidence introduced
at trial, not merely the evidence a defendant introduces at trial."
Midwest Suspension, 824 F. Supp. at 735 n.30.
13 For example, the court in United States v. Smithfield Foods, Inc., 972
F. Supp. 338, 353 (E.D. Va. 1997), noted that some courts, including the
Eleventh Circuit in Tyson Foods, have used "the 'top down' method of
penalty calculation, in which the court begins the penalty calculation at
the statutory maximum, and adjusts downward considering the [statutory]
factors," whereas some district courts have used "the 'bottom-up'
method of penalty calculation, in which the court begins the penalty calculation
using defendants' economic benefit of noncompliance, and adjusts upward
or downward considering the [statutory] factors." After concluding
that "the statute does not require either the 'top-down' or the 'bottom-up'
method," the court chose, as an exercise of its "discretion,"
to use the "bottom-up" method. Id. at 353-354.
14 Petitioner relies on a footnote in J.B. Williams, 498 F.2d at 430 n.19,
that consists essentially of dicta.
)
(1)