No. 98-1460
In the Supreme Court of the United States
ARBITER SYSTEMS, INC., PETITIONER
v.
RICHARD J. DANZIG, SECRETARY OF THE NAVY
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
BRIEF FOR THE RESPONDENT IN OPPOSITION
SETH P. WAXMAN
Solicitor General
Counsel of Record
DAVID W. OGDEN
Acting Assistant Attorney
General
ANTHONY J. STEINMEYER
CRAIG GOTTLIEB
Attorneys
Department of Justice
Washington, D.C. 20530-0001
(202) 514-2217
QUESTION PRESENTED
Whether the court of appeals correctly sustained the determination of the
Armed Services Board of Contract Appeals that the Navy was not estopped
from rejecting petitioner's claims for cost overruns on two Navy contracts.
In the Supreme Court of the United States
No. 98-1460
ARBITER SYSTEMS, INC., PETITIONER
v.
RICHARD J. DANZIG, SECRETARY OF THE NAVY
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
BRIEF FOR THE RESPONDENT IN OPPOSITION
OPINIONS BELOW
The judgment order of the court of appeals (Pet. App. A1-A2) is not yet
reported. The opinion of the Armed Services Board of Contract Appeals (Pet.
App. A3-A24) is reported at 97-2 B.C.A. (CCH) ¶ 29,183.
JURISDICTION
The judgment of the court of appeals was entered on December 15, 1998. The
petition for a writ of certiorari was filed on March 12, 1999. The jurisdiction
of this Court is invoked under 28 U.S.C. 1254(1).
STATEMENT
1. This case involves two cost-plus-fixed-fee research and development contracts
entered into between petitioner and the Department of the Navy: Contract
No. N00123-87-D-0126 (contract 0126) and Contract No. N00123-87-D-0279 (contract
0279). In 1986 and 1987, when the Navy solicited bids for those contracts,
petitioner was already performing a similar, but smaller, contract for the
Navy, Contract No. N00123-83-D-0081 (contract 0081). At that time, petitioner
was a relatively small business, which employed eight to ten people and
operated out of a small rented facility. Petitioner's owners recognized
that, in order to be able to perform contracts 0126 and 0279, they would
have to expand their operation. Accordingly, in the proposals that they
submitted to the Navy with respect to the two contracts, they estimated
petitioner's overhead cost rates based upon that anticipated expansion.
Pet. App. A4, A6-A7.
The Navy initially rejected petitioner's proposals. The Navy noted that
petitioner's projected overhead cost rates were higher than the pre-award
audit rates established by the Defense Contract Audit Agency (DCAA), the
agency responsible for assisting military contracting officers in auditing
contractors. DCAA had based its pre-award audit rates on petitioner's performance
of contract 0081 and on an analysis of projected labor costs. Pet. App.
A7.
Two of petitioner's owners, Bruce Roeder and Michael Flatten, then met with
the Navy contracting officer. They explained that, because of the intended
expansion, petitioner would lose money if it billed at DCAA's rates. According
to Roeder, the contracting officer replied that, because petitioner ultimately
would be "reimbursed for all [of its] costs anyway," it did not
matter whether the contract reflected DCAA's pre-award audit rates or petitioner's
proposed increased rates. There was no discussion of whether petitioner
would be reimbursed in excess of the contract's estimated cost limitations.
Pet. App. A7-A8.1
The Navy awarded petitioner contract 0126 on September 12, 1986, and contract
0279 on June 30, 1987. Each contract incorporated by reference the "Limitation
of Cost" clause of the Federal Acquisition Regulations, 48 C.F.R. 52.232-20
(Pet. App. A33-A35). Pet. App. A4, A6.
The Limitation of Cost clause explicitly requires a contractor, if it seeks
to recover costs in excess of the contract's estimated cost limitations,
to "notify the Contracting Officer in writing whenever it has reason
to believe" that its costs "will exceed 75 percent of the estimated
cost specified in the Schedule." The clause further states that "[t]he
Contractor is not obligated to continue performance under th[e] contract
* * * or otherwise incur costs in excess of the estimated cost specified
in the Schedule, until the Contracting Officer (i) notifies the Contractor
in writing that the estimated cost has been increased and (ii) provides
a revised estimated total cost of performing th[e] contract." The clause
also provides that "[i]n the absence of the specified notice, the Government
is not obligated to reimburse the Contractor for any costs in excess of
the estimated cost." Pet. App. A33-A35.
The two contracts were implemented by a series of 21 delivery orders. Both
contracts stated that "[e]ach delivery order shall be deemed to include
therein the clause Limitation of Costs" described above. And each individual
delivery order, like the contracts themselves, specified an estimated cost
and provided that the government was not obligated to reimburse any amount
expended by petitioner in excess of the estimated cost unless the amount
was increased by formal modification. Pet. App. A5, A9.
The parties' course of performance indicates that petitioner understood
the Limitation of Cost clause and its requirement of giving notice and receiving
approval before exceeding cost limitations. On several occasions, petitioner
requested additional funding as it approached the funding limit and stopped
working until additional funds were provided. Moreover, in correspondence
sent to petitioner during the performance of the contract, the Navy specifically
reminded petitioner to provide notice if its actual overhead costs exceeded
the funding limits. Pet. App. A11-A12.
As instructed by the Navy, petitioner billed at the provisional DCAA rate
throughout the terms of the contracts. Pet. App. A10. Petitioner was aware,
however, of its higher actual overhead costs. Id. at A19. Petitioner never
gave notice to the Navy contracting officer of any actual overhead cost
overruns during contract performance as required by the Limitation of Cost
clauses of its contracts. Id. at A15.
At the conclusion of the contracts, petitioner's total overhead costs were
calculated using an updated DCAA rate, which revealed that petitioner's
costs well exceeded the contract's limits. Petitioner then invoiced the
Navy for the entirety of its actual overhead costs, including its overruns.
The Navy declined to fund the overruns because petitioner had failed to
give notice as required by the contracts. Pet. App. A14-A15.
Petitioner then submitted claims to the Navy for $84,994.39 under contract
0126 and for $676,448.71 under contract 0279. The Navy contracting officer
denied the claims. Pet. App. A16.
2. Petitioner appealed that decision to the Armed Services Board of Contract
Appeals, contending, inter alia, that (1) petitioner was excused from the
notice requirement of the Limitation of Cost clause because its cost overruns
were unforeseeable, and (2) the government was estopped from asserting that
notice requirement because the contracting officer had orally assured petitioner
during contract negotiations that it would be paid its actual costs. The
Board rejected both arguments. Pet. App. A17-A24.
First, the Board of Contract Appeals concluded that petitioner had not met
its burden of proving that the cost overruns were not reasonably foreseeable.
Pet. App. A17. The Board found "no indication that [petitioner] could
not have determined its actual incurred costs during performance" of
the contracts. Id. at A19. Indeed, said the Board, petitioner "appears
to have been aware of its actual overhead and G&A expenses." Ibid.2
Second, the Board of Contract Appeals concluded that petitioner had likewise
failed to meet its burden of proving that the government was estopped from
invoking the Limitation of Cost clause to deny funding of the cost overruns.
Pet. App. A21-A22. Applying the Federal Circuit's standard applicable to
contractors' claims of estoppel against the government, the Board determined
that petitioner had failed to establish two "essential elements"
of that standard, i.e., that the government was aware of the cost overruns
and that the government engaged in conduct designed to induce the contractor's
continued performance. Ibid. The Board found that "the Government had
no idea of the amounts of any impending cost overruns on the various delivery
orders because [petitioner] did not provide that information during contract
performance." Id. at A22. The Board further found that "[t]he
Government did not intend for [petitioner] to continue performance when
the contract was in a cost overrun status and did nothing to encourage [petitioner]
to do so." Ibid.
3. The Federal Circuit affirmed the Board of Contract Appeals' decision
without opinion. Pet. App. A1-A2.
ARGUMENT
Petitioner challenges the Federal Circuit's unpublished order affirming
the decision of the Armed Forces Board of Contract Appeals. That order is
without precedential effect under the rules of the Federal Circuit (see
Pet. App. A1). The underlying decision of the Board of Contract Appeals
is correct, does not conflict with any decision of this Court or any other
court of appeals, and turns on the particular facts of this case. This Court's
review is therefore not warranted.
1. Petitioner contends (Pet. 12-14) that the Board of Contract Appeals erred
in adding a fifth element, foreseeability, to the four elements traditionally
considered by the Federal Circuit to assess whether the government is estopped
from invoking a contractual provision. See, e.g., Advanced Materials, Inc.
v. Perry, 108 F.3d 307, 311-312 (Fed. Cir. 1997) (enumerating four elements).
Petitioner's argument rests on a misreading of the Board's decision. The
Board recognized that petitioner could prevail if it established either
(1) that compliance with the notice requirement of the Limitation of Cost
clause was impossible because petitioner could not reasonably have foreseen
its cost overruns, or (2) that the government was estopped from enforcing
the Limitation of Cost clause under the traditional four-element test. See
Pet. App. A17, A21-A23. The Board found that petitioner had not satisfied
either alternative inquiry. The Board did not, as petitioner contends, conflate
the two inquiries.
Petitioner's assertion of a circuit conflict is predicated on the same misreading
of the Board of Contract Appeals' decision. Petitioner claims (Pet. 19)
that the Board's decision conflicts with the decisions of "other circuits"-although
he cites only the Ninth Circuit's decision in United States v. Georgia-Pacific
Co., 421 F.2d 92 (1970)-on the sole ground that "other circuits simply
do not allow 'foreseeability' to defeat estoppel." But neither did
the Board in this case. No tension therefore exists between Georgia-Pacific
and the decision here.
Petitioner also contends (Pet. 19) that the Board of Contract Appeals' decision
conflicts with this Court's "requirements for the establishment of
equitable estoppel against the government." But this Court has not
yet even decided "whether an estoppel claim could ever succeed against
the Government." OPM v. Richmond, 496 U.S. 414, 423 (1990); accord
Heckler v. Community Health Services, 467 U.S. 51, 60 (1984). Much less
has the Court articulated the particular "requirements" for the
establishment of any such claim. In Community Health Services, the decision
of this Court on which petitioner purports to rely, the Court merely suggested
that a party seeking to establish estoppel against the government "surely
cannot prevail without at least demonstrating that the traditional elements
of an estoppel are present." 467 U.S. at 61 (emphasis added). The Court
did not intimate that those would be the only elements that would have to
be proved. Cf. Richmond, 496 U.S. at 424-434 (holding that estoppel cannot
apply to a claim for payment of money from the federal treasury).
2. The Board of Contract Appeals' conclusion that petitioner failed to satisfy
the four traditional elements of estoppel is unexceptionable. In contending
otherwise, petitioner relies (Pet. 15-17) solely on the Navy contracting
officer's statement during the contract negotiations that petitioner's costs
would be reimbursed. As the Board found (Pet. App. A22), however, petitioner's
concerns expressed during the 1986 negotiations about anticipated increased
overhead costs cannot be deemed to have given the government notice of actual
cost overruns that did not occur until as late as 1990.
Nor could the contracting officer's statement reasonably have been construed
as excusing petitioner's noncompliance with the Limitation of Cost clause
and its notice requirement. As the Board found (Pet. App. A22), the contracting
officer made that statement at a meeting that did not "concern actual
costs in excess of funding the delivery orders." The contracting officer's
statement merely indicated that petitioner could be reimbursed at its increased
actual rates, not that petitioner would not have to comply with applicable
contractual provisions in order to obtain such reimbursement. Indeed, the
government explicitly advised petitioner during contract performance that
it was required under the Limitation of Cost clause to provide notice of
its actual overhead costs. Id. at A12. The government was not estopped,
therefore, from asserting its rights under that clause.3
In any event, the Board of Contract Appeals' decision, properly read, involves
nothing more than the application of settled legal principles to the particular
facts of this case. Such decisions do not ordinarily merit this Court's
review. See Sup. Ct. R. 10.
CONCLUSION
The petition for a writ of certiorari should be denied.
Respectfully submitted.
SETH P. WAXMAN
Solicitor General
DAVID W. OGDEN
Acting Assistant Attorney
General
ANTHONY J. STEINMEYER
CRAIG GOTTLIEB
Attorneys
MAY 1999
1 The contracting officer could not recall at the time of the Board of Contract
Appeals hearing whether she had, in fact, made the statements that Roeder
attributed to her. Pet. App. A8.
2 As a result of a typographical error, the word "its" appears
in the Appendix to the Petition as "As."
3 Petitioner also argues (Pet. 16-17) that the government is estopped from
denying reimbursement of cost overruns on the two contracts at issue here,
because the government allowed payment of all excess overhead costs under
the earlier 0081 contract although petitioner gave no notice of its overhead
cost overruns. As the Board of Contract Appeals explained (Pet. App. A20),
however, "[p]rior retroactive funding of overruns on another contract
does not bind the Government to fund future overruns on these contracts."
See Textron Defense Sys., 96-2 B.C.A. (CCH) ¶ 28,332, at 141,492 (1996),
aff'd, 143 F.3d 1465 (Fed. Cir. 1998).