No. 99-1134
In the Supreme Court of the United States
MELKA MARINE, INC., PETITIONER
v.
UNITED STATES OF AMERICA
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
BRIEF FOR THE UNITED STATES IN OPPOSITION
SETH P. WAXMAN
Solicitor General
Counsel of Record
DAVID W. OGDEN
Acting Assistant Attorney General
ANTHONY J. STEINMEYER
FRANKLIN E. WHITE, JR.
Attorneys
Department of Justice
Washington, D.C. 20530-0001
(202) 514-2217
QUESTION PRESENTED
Whether the court of appeals correctly affirmed the finding of the Court
of Federal Claims that petitioner, a government contractor, failed to show
that it was on "standby" under settled Federal Circuit case law
or to prove that it was entitled to further compensation for idle equipment
and labor.
In the Supreme Court of the United States
No. 99-1134
MELKA MARINE, INC., PETITIONER
v.
UNITED STATES OF AMERICA
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE FEDERAL CIRCUIT
BRIEF FOR THE UNITED STATES IN OPPOSITION
OPINIONS BELOW
The opinion of the court of appeals (Pet. App. A1-A29) is reported at 187
F.3d 1370. The June 10, 1998 opinion of the Court of Federal Claims (Pet.
App. A30-A49) is reported at 41 Fed. Cl. 122. The August 4, 1997 opinion
of the Court of Federal Claims (Pet. App. A50-A56) is reported at 38 Fed.
Cl. 545.
JURISDICTION
The judgment of the court of appeals was entered on August 12, 1999. A petition
for rehearing was denied on October 7, 1999 (Pet. App. A57-A58). The petition
for a writ of certiorari was filed on January 5, 2000. The jurisdiction
of this Court is invoked under 28 U.S.C. 1254(1).
STATEMENT
1. The Department of the Navy awarded petitioner a contract for various
work items, including dredging in the Potomac River, construction of a breakwater,
and repairs to an existing boat ramp, quaywall, and finger pier at the Naval
Surface Warfare Center in Indian Head, Maryland. Pet. App. A3. The contract
required the Navy to obtain a dredging permit from the Army Corps of Engineers
prior to the commencement of the dredging and breakwater work, but not the
repair work. Ibid.
On November 4, 1994, prior to petitioner's mobilization of its dredging
and breakwater equipment to the project site, the Navy notified petitioner
that the dredging permit had not been received and that the dredging work
required by the contract could not proceed until the permit was approved.
Pet. App. A3. The Navy also informed petitioner that "construction
repairs [were] not dependent on this permit." Ibid. Accordingly, petitioner
resequenced the contract work and began repairs to the boat ramp on November
21, 1994. Id. at A4. It suspended those operations the next day, however,
when it discovered a six-inch pipe in the boat ramp and a prior boat ramp
beneath the existing one. Ibid.
On November 29, 1994, the Navy issued a formal Suspension of Work order
based on the discovery of the pipe and old boat ramp, the need for a boat
ramp design review, and the Navy's failure to obtain the dredging permit.
Pet. App. A4. Two days later, on December 1, 1994, the Navy partially lifted
the suspension. Ibid. The Navy informed petitioner that, while the dredging
permit was not expected for at least another month and a half, work could
commence on the repairs to the quaywall and finger pier and that "[a]ll
equipment on site that will not be utilized on the repairs to the boat ramp,
quaywall, or finger pier can be demobilized." Id. at A4-A5.
During December 1994, petitioner performed the boat ramp, quaywall, and
other miscellaneous repair work required by the contract. Pet. App. A5.
This work was substantially completed by January 4, 1995. Ibid.
Also during December 1994, petitioner demobilized its dredging and breakwater
equipment as directed in the Navy's December 1, 1994 letter. By December
27, 1994, petitioner had completed the demobilization of this equipment
from the Navy job site. Pet. App. A5. Petitioner later mobilized this same
equipment for use on two private contracts. Id. at A5, A45.
On February 2, 1995, the Navy and petitioner met to discuss the future of
the contract in light of the continuing delay in the Navy's receipt of the
required dredging permit. Pet. App. A6. At the meeting, the Navy informed
petitioner that in order for the contract to continue, the dredging and
breakwater work would have to be postponed until October 15, 1995, and that
petitioner would have to agree to perform the dredging and breakwater work
at that time for the original contract price. Ibid. Petitioner agreed and
proposed a February 29, 1996 contract completion date. Ibid.
The parties' agreement was incorporated as a bilateral modification of the
contract, Contract Modification P00001, which extended the contract completion
date to February 29, 1996, and provided petitioner $42,688 in compensation
for its remobilization/ demobilization costs associated with the postponement
of the dredging and breakwater work until October 15, 1995. Pet. App. A6
n.1, A33. A second bilateral contract modification, P00002, provided petitioner
$7,163 as compensation for all costs arising from the changed condition
of the quaywall and for the delay caused by the uncovered pipe at the boat
ramp excavation. Id. at A6-A7 n.1, A33. Contract Modification P00003, a
unilateral modification issued by the Navy, awarded petitioner $19,837 for
overhead and field costs arising from petitioner's having performed work
out of sequence and from the Navy's directive that petitioner stop work
on the boat ramp until the Navy had reviewed its repair design. Id. at A7
n.1, A33. This amount included reimbursement to petitioner for its dredging
and breakwater equipment for twelve days. Ibid. Work on the contract was
completed by February 1996. Id. at A7.
2. Petitioner filed a complaint seeking additional compensation for its
indirect costs for unabsorbed home-office overhead and for its direct costs
for idled equipment and labor for the period November 16, 1994 through March
30, 1995, which it argued were caused by the government's Suspension of
Work order. Pet. App. A30, A33. Following a trial, the Court of Federal
Claims denied petitioner's claims and dismissed its complaint. Id. at A30-A49.
The court first determined that under the Federal Circuit's established
precedents, a contractor can recover unabsorbed home-office overhead only
if it proves that the government required the contractor to "stand
by" during a period of government-caused delay. Id. at A34-A35. The
court then found that for the period November 16, 1994 through January 4,
1995, petitioner had been compensated for its overhead by Contract Modification
P00003 for part of the period and was not on standby for the remainder of
that period because it performed resequenced contract work for which a dredging
permit was not necessary. Id. at A37-A40. As for the period January 4, 1995
through February 2, 1995, the court found that petitioner was on standby
but it was not entitled to damages because it bid for and obtained other
work. Id. at A40-A42. The court then found that petitioner was not on standby
from February 2, 1995 to March 30, 1995, because on February 2, 1995, the
Navy postponed the dredging and breakwater work until the "date certain"
of October 15, 1995, thereby removing any uncertainty surrounding petitioner's
dredging and breakwater work. Id. at A42-A43. Finally, the trial court determined
that petitioner was not entitled to recover additional direct costs for
idled equipment and labor, beyond what it had received under Contract Modification
P00003, because petitioner had not proved that the government had required
petitioner to keep the equipment and labor idle. Id. at A43-A48.
3. On appeal by petitioner, the court of appeals affirmed-in-part, vacated-in-part,
and remanded. Pet. App. A1-A29. The court reiterated the well-settled rule
that in order to recover for standby damages, a contractor must show that
the government required it to stand by during a government-caused delay
of indefinite duration; and that while and because of standing by, the contractor
was unable to take on other work. Id. at A9. After that showing, the government
then bears the burden of showing either that it was not impractical for
the contractor to obtain replacement work during the delay or that the contractor's
inability to obtain such work, or to perform it, was not caused by the government's
suspension. Ibid.
The court of appeals affirmed the trial court's findings that petitioner
did not prove it was on standby from November 16, 1994 to January 4, 1995,
or from February 2, 1995 to March 30, 1995. Pet. App. A9-A10. As to the
first period, the court of appeals held that the trial court "did not
clearly err in finding that [petitioner] was not on standby when it was
working on the contract and the government had not suspended all contract
work." Id. at A10-A11. As to the second period, the court of appeals
held that "'standby' requires an uncertain delay period where the government
can require the contractor to resume full-scale work at any time,"
and here petitioner knew "with certainty that it could not be called
on to perform the [dredging] work before October 15." Id. at A12-A13.
The court also affirmed the denial of petitioner's claims for idle equipment
and labor. Pet. App. A7 n.2. The court, however, remanded petitioner's claim
for unabsorbed home-office overhead from January 4, 1995 to February 2,
1995, a period for which the government conceded that petitioner was on
standby, holding that the trial court had applied an incorrect legal standard
to determine whether the government met its burden. Id. at A13-A19.
ARGUMENT
The court of appeals correctly applied the established legal standard governing
recovery of standby costs to the facts of this case. Its decision does not
conflict with the decisions of this Court or any other court of appeals.
Further review is not warranted.
1. The Federal Circuit, the appellate court that Congress has entrusted
to review government contract disputes, see 28 U.S.C. 1295(a)(3) and (10);
41 U.S.C. 609, has long held that a contractor can recover for unabsorbed
overhead costs of the type petitioner seeks here only if it proves, among
other things, that the government required the contractor to "stand
by" during a government-caused delay of indefinite duration. See, e.g.,
Altmayer v. Johnson, 79 F.3d 1129, 1133 (Fed. Cir. 1996); Interstate General
Gov't Contractors, Inc. v. West, 12 F.3d 1053, 1056 (Fed. Cir. 1993); see
also Eichleay Corp., 60-2 B.C.A. (CCH) ¶ 2688, aff'd on reconsideration,
61-1 B.C.A. (CCH) ¶ 2894 (ASBCA 1960). Both the Court of Federal Claims
and the Federal Circuit concluded that petitioner was not on standby from
November 16, 1994 to January 3, 1995, and from February 3, 1995 to March
30, 1995, because during these periods petitioner was "not on indefinite
duration standby." Pet. App. A10. Specifically, from November 16, 1994
to January 4, 1995, petitioner was not on standby because it performed significant
and uninterrupted repair work required by the contract, albeit in a different
sequence than was originally planned. Id. at A10-A12, A37-A40. And, from
February 2, 1995 to March 30, 1995, petitioner could not have been on standby
because it knew with certainty that it would not be called on to perform
the work related to the permit until October 15, 1995. Id. at A12-A13, A42-A43.
The courts' findings and conclusions of law are correct and comport with
Federal Circuit case law.
2. As to the first period, November 16, 1994 through January 4, 1995, petitioner
relies principally on Altmayer v. Johnson, 79 F.3d 1129 (Fed. Cir. 1996)
(Pet. 24-27). Reliance on Altmayer provides no basis for review. First,
any inconsistency with a Federal Circuit decision would demonstrate at most
an intra-circuit conflict, which is not a basis for review by this Court.
See Davis v. United States, 417 U.S. 333, 340 (1974); Wisniewski v. United
States, 353 U.S. 901, 902 (1957) (per curiam). Furthermore, Altmayer is
distinguishable. Altmayer involved a government-caused delay which effectively
disrupted performance of an entire construction project through a "critical
path" delay of uncertain duration. See 79 F.3d at 1131 (defining "critical
path" as "all of the critical tasks to be performed on the contract
in a logical sequence that would ultimately lead to timely completion of
the contract."). In that case, the Federal Circuit concluded that the
finding that the contractor performed additional work was simply not supported
by the evidence; it also found it insignificant that the contractor had
completed some minor items during the period of government imposed delay.
See id. at 1134.
In this case, by contrast, the Federal Circuit concluded that the evidence
demonstrated that from November 16, 1994 to January 4, 1995, petitioner
performed significant repair work that was entirely independent of the dredging
and breakwater work called for by the contract. Thus, petitioner was not
on standby when it performed uninterrupted work on these contract items,
for which it was fully compensated.
Petitioner also errs in relying (Pet. 28) on Williams Enterprises v. Sherman
R. Smoot Co., 938 F.2d 230 (D.C. Cir. 1991). In that case the District of
Columbia Circuit held that in order to recover damages for home-office overhead
costs arising from an extension (rather than a suspension) of a non-government
contract, the contractor "must be able to show that it was unable to
avoid the additional home office overhead costs." Id. at 235. That
holding is entirely consistent with the holding below. In Williams there
had been a sudden and unpredictable collapse of the building under construction;
therefore the contractor clearly had no opportunity to mitigate its loss.
Ibid. No similar circumstances prevented petitioner from mitigating its
loss in this case.
3. The Federal Circuit also correctly determined that petitioner was not
on standby from February 2, 1995 to March 30, 1995. Pet. App. A12-A13. The
Court of Federal Claims found that on February 2, 1995, petitioner had been
informed by the Navy that the dredging and breakwater portions of the contract
would be postponed until October 15, 1995. Id. at A42-A43. Under the Federal
Circuit's established precedents, once the government fixes a future date
for the resumption of work, standby cannot be shown because standby requires
an uncertain delay period during which the government can require the contractor
to resume full-scale work at any time. See, e.g., West v. All State Boiler,
Inc., 146 F.3d 1368, 1380 (Fed. Cir. 1998).
4. Finally, the Federal Circuit properly affirmed the Court of Federal Claims'
determination that petitioner was not entitled to additional compensation
for direct costs related to idled equipment and labor. The Court of Federal
Claims correctly found that, apart from days for which equipment costs were
paid through Contract Modification P00003, Pet. App. A45, petitioner simply
provided no evidence that its dredging and breakwater equipment was ever
made idle as a result of the delay relating to the dredging permit, id.
at A45-A46. Rather, the trial court found that petitioner moved its equipment
from the Navy's contract site to other project sites and used the equipment
on those jobs. Id. at A45. Because petitioner's equipment was never "necessarily
set aside and awaiting use in performing the [Navy] contract," the
government was not liable for idled equipment costs. See, e.g., J.D. Shotwell
Company, 65-2 B.C.A. (CCH) ¶ 5243, at 24,687 (ASBCA 1965).
Similarly, the Court of Federal Claims correctly found that petitioner did
not establish government responsibility for idled labor. First, the trial
court found that during November and December 1994, petitioner's employees
were performing the resequenced repair work required by the contract. Pet.
App. A47-A48. Second, the trial court found that "[w]hen [petitioner's]
employees were not working on the contract in January [1995], they were
performing other construction projects." Id. at A48. Petitioner's claim
for idled labor for the period after February 2, 1995-the date when the
Navy postponed the remainder of the contract until October 1995-is inconsistent
with its "duty to mitigate [its] damages by transferring labor and
equipment affected by the stoppage to other uses pending the time that work
can recommence." Signal Contracting, Inc., 93-2 B.C.A. (CCH) ¶
25,877, at 128,736 (ASBCA 1993). The trial court found that "[n]o evidence
presented at trial showed that all idle labor claimed was necessary. [Petitioner]
could have layed off employees pending recommencement of the Navy project."
Pet. App. A48. Finally, the trial court found that petitioner benefitted
from the "shop work" that its employees performed during this
period. Ibid.
The Court of Federal Claims' findings were not clearly erroneous. Following
settled principles of law the Federal Circuit correctly affirmed.*
CONCLUSION
The petition for a writ of certiorari should be denied.
Respectfully submitted.
SETH P. WAXMAN
Solicitor General
DAVID W. OGDEN
Acting Assistant Attorney General
ANTHONY J. STEINMEYER
FRANKLIN E. WHITE, JR.
Attorneys
MARCH 2000
* Moreover, we note that the decision below is interlocutory in that one
of petitioner's claims remains open on remand. Petitioner's complete recovery
will not finally be determined until the completion of that part of the
case. Cf. Brotherhood of Locomotive Firemen v. Bangor & Aroostook R.R.,
389 U.S. 327, 328 (1967) (denying petition for writ of certiorari where
the court of appeals remanded the case).