No. 99-1914
In the Supreme Court of the United States
TOWN OF NORWOOD, PETITIONER
v.
FEDERAL ENERGY REGULATORY COMMISSION
AND NEW ENGLAND POWER COMPANY
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT
BRIEF FOR THE
FEDERAL ENERGY REGULATORY COMMISSION
IN OPPOSITION
SETH P. WAXMAN
Solicitor General
Counsel of Record
Department of Justice
Washington, D.C. 20530-0001
(202) 514-2217
DOUGLAS W. SMITH
General Counsel
DENNIS LANE
Solicitor
JOHN H. CONWAY
Associate Solicitor
LARRY D. GASTEIGER
Attorney
Federal Energy Regulatory
Commission
Washington, D.C. 20426
QUESTION PRESENTED
Whether the court of appeals correctly held that the Federal Energy Regulatory
Commission acted reasonably and in accordance with its authority under the
Federal Power Act, 16 U.S.C. 791a et seq., in approving a series of filings
made by the New England Power Company (NEPCO) that (1) allow NEPCO's wholesale
electric power customers the option of terminating their power-purchase
contracts early in return for paying a contract-termination charge to reimburse
NEPCO for costs it incurred in expectation of serving those customers for
the full contract term; (2) permit NEPCO to divest itself of certain generation
assets; and (3) restructure NEPCO's contractual relationship with certain
of its affiliates to accommodate state-imposed retail competition requirements.
In the Supreme Court of the United States
NO. 99-1914
TOWN OF NORWOOD, PETITIONER
v.
FEDERAL ENERGY REGULATORY COMMISSION
AND NEW ENGLAND POWER COMPANY
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT
BRIEF FOR THE
FEDERAL ENERGY REGULATORY COMMISSION
IN OPPOSITION
OPINIONS BELOW
The opinion of the court of appeals (Pet. App. 1a-27a) is reported at 202
F.3d 392. The orders of the Federal Energy Regulatory Commission (Pet. App.
28a-116a) are reported at 81 F.E.R.C. ¶ 61,281 (1997), 82 F.E.R.C.
¶ 61,179 (1998), 83 F.E.R.C. ¶ 61,174 (1998), 83 F.E.R.C. ¶
61,265 (1998), 83 F.E.R.C. ¶ 61,275 (1998), and 84 F.E.R.C. ¶
61,175 (1998).
JURISDICTION
The judgment of the court of appeals was entered on February 2, 2000. A
petition for rehearing was denied on March 1, 2000 (Pet. App. 117a). The
petition for a writ of certiorari was filed on May 30, 2000. The jurisdiction
of this Court is invoked under 28 U.S.C. 1254(1).
STATEMENT
1. Under Section 205(c) of the Federal Power Act (FPA), 16 U.S.C. 824d(c),
public utilities are required to file all rates pertaining to sales within
the jurisdiction of the Federal Energy Regulatory Commission (FERC), and
all contracts affecting such rates, with the Commission. Any changes to
previously-filed tariffs must be submitted in accordance with FPA Section
205(d), 16 U.S.C. 824d(d), and the Commission in turn is empowered to investigate
the reasonableness of the proposed change pursuant to FPA Section 205(e),
16 U.S.C. 824d(e). Under Section 203(a) of the FPA, 16 U.S.C. 824b(a), the
Commission must approve the disposition of facilities subject to its jurisdiction
if they have a value in excess of $50,000, and the Commission must also
approve mergers.
The Commission's authority to entertain proposed modifications to a filed
tariff is subject to judicially-developed doctrines respecting the parties'
contractual interests. In this regard, the Mobile-Sierra doctrine holds
that where parties have negotiated a contract that denies either party the
right to change prices unilaterally, FERC may abrogate or modify the contract
only if the public interest so requires. See United Gas Pipe Line Co. v.
Mobile Gas Serv. Corp., 350 U.S. 332 (1956); FPC v. Sierra Pac. Power Co.,
350 U.S. 348 (1956). As a separate matter, under the filed rate doctrine,
a utility may lawfully charge only the rate that is reflected in the tariff
on file when the service is performed. Arkansas La. Gas Co. v. Hall, 453
U.S. 571, 577-578 (1981). A corollary principle, pertinent here, prohibits
retroactive rate increases for tariffed services. Ibid.
Since enactment of the FPA in 1935, the electric utility industry has undergone
significant changes. Alternative electric power suppliers have created a
wholesale market for low-cost power to compete with the traditional, vertically
integrated utilities that had built high-cost generation capacity. FERC
has taken various steps to encourage this competition. Invoking its authority
under Sections 205 and 206 of the FPA, 16 U.S.C. 824d and 824e, to remedy
unduly discriminatory or preferential rules, regulations, practices or contracts
affecting public utility rates for transmission in interstate commerce,
FERC issued Order No. 888 and accompanying regulations requiring all public
utilities owning or controlling transmission facilities to offer non-discriminatory
open access transmission services.1 See generally Transmission Access Policy
Study Group v. FERC, No. 97-1715, 2000 WL 762706, at *5-*6 (D.C. Cir. June
30, 2000). At the same time, recognizing that utilities required to provide
non-discriminatory access to their transmission lines might incur transition
(i.e., "stranded") costs because their historic customers could,
under the new regulations, import cheaper power purchased elsewhere, the
Commission provided utilities a limited opportunity to recover stranded
costs that they incur as a result of its new rules. Ibid. The stranded cost
regulations are codified at 18 C.F.R. 35.26.
2. New England Power Company (NEPCO) is a public utility subject to FERC's
jurisdiction under the FPA. NEPCO and its affiliates are also subject to
regulation by the States of Massachusetts and Rhode Island to the extent
they provide retail services to customers within those States.
Between December 1996 and May 1998, NEPCO made a series of filings with
FERC for the ultimate purpose of accommodating the introduction of retail
electric power competition in Massachusetts and Rhode Island.2 Taken together,
the filings sought FERC approval of changes to certain wholesale power sales
agreements between NEPCO and its affiliates; the sale of non-nuclear generation
assets by NEPCO to USGen New England, Inc. (USGen); and a general revision
to NEPCO's tariff that would allow NEPCO's wholesale power customers to
terminate their power contracts early in return for paying a "contract
termination charge." See Pet. App. 4a-7a.
In the first filing, NEPCO proposed amending its power sales agreements
with its affiliates in Massachusetts and Rhode Island that purchase power
at wholesale from NEPCO under FERC-approved tariffs and resell that power
to retail customers in those States. It proposed to permit such affiliates
to terminate their long-term requirements contracts on short notice in order
to allow them to purchase cheaper power from other electric suppliers. The
early termination, however, would be subject to the payment of a contract
termination charge (CTC) to reimburse NEPCO for a portion of the costs it
had incurred in preparing to meet its obligation to provide power to the
affiliates over the full term of their long-term contracts.3 Ultimately,
NEPCO's December 1996 filing was resolved through settlement agreements
with its affiliates and state regulatory authorities. The settlements, presented
to FERC for approval, permitted early contract termination for NEPCO's affiliates
subject to payment of a CTC. It also obligated NEPCO to provide its affiliates
with the option of taking service from NEPCO under new "wholesale standard
offer rates" for a limited transition period at escalating prices set
by the Massachusetts and Rhode Island regulatory authorities under their
retail restructuring programs.4 In addition, the settlements obligated NEPCO
to file with the Commission a plan to divest itself of most of its generation
assets. Pet. App. 4a-5a.
In accordance with the terms of its settlement agreements, on October 1,
1997, NEPCO sought Commission approval under FPA Section 203, 16 U.S.C.
824b, to sell generating assets to USGen. In connection with its proposed
purchase of those assets, USGen agreed to assume responsibility for providing
NEPCO's affiliates with the wholesale standard offer service, and NEPCO
proposed to implement a rate freeze that would prevent increases in its
rates for its remaining wholesale customers. Pet. App. 5a.
Petitioner, one of the remaining wholesale customers, objected to NEPCO's
proposed settlements with its affiliates and to the proposed divestiture
transaction. Petitioner purchased electricity at wholesale from NEPCO and
resold that electricity to retail customers in Massachusetts. Contending
that the wholesale standard offer rates proposed for NEPCO's affiliates
would provide them with an unfair advantage as retail competitors, petitioner
objected to the filings. In addition, on March 4, 1998, petitioner notified
NEPCO that it was canceling its power supply contract with NEPCO, which
had been extended to the year 2008, and switching to a different wholesale
supplier effective April 1, 1998.5
NEPCO responded to petitioner's cancellation notice by filing a proposed
revision to its FERC tariff that would provide all of its wholesale customers,
including petitioner, the opportunity to terminate their long-term requirements
contracts on 30-days' notice, rather than the seven-years' notice of termination
required under the FERC tariff, on the payment of a CTC. Petitioner objected
to this filing as well, arguing that the CTC for the non-affiliated wholesale
purchasers, standing alone and in concert with the settlement and the divestiture
filings, was unlawful and unduly discriminatory. Pet. App. 6a-7a.
In three sets of orders issued between November 1997 and June 1998, the
Commission approved all three NEPCO filings. New England Power Co., 81 F.E.R.C.
¶ 61,281 (1997), reh'g denied, 83 F.E.R.C. ¶ 61,265 (1998), Pet.
App. 28a-43a (approving the settlement agreements between NEPCO and its
affiliates); New England Power Co., 82 F.E.R.C. ¶ 61,179, reh'g denied,
83 F.E.R.C. ¶ 61,275 (1998), Pet. App. 44a-101a (approving the sale
of NEPCO's non-nuclear generating facilities to USGen); New England Power
Co., 83 F.E.R.C. ¶ 61,174, reh'g denied, 84 F.E.R.C. ¶ 61,175
(1998), Pet. App. 102a-116a (approving the amendment of NEPCO's tariff to
permit its unaffiliated customers to terminate their long-term contracts
prematurely subject to payment of a CTC). The Commission considered and
rejected petitioner's various challenges to the filings, including, inter
alia, that NEPCO's proposals conflicted with Order No. 888's stranded-cost
recovery regulations, constituted an impermissible award of contract damages,
violated the Mobile-Sierra and filed rate doctrines, and resulted in discriminatory
and anticompetitive charges. In doing so, the Commission acknowledged that
there existed a contract dispute between petitioner and NEPCO triggered
by petitioner's cancellation, but specifically declined to address either
the merits of that dispute or the impact of that dispute on the general
tariff provision changes before it. Pet. App. 108a-109a, 114a.6
3. The court of appeals upheld the Commission's orders in all respects.
Pet. App. 1a-27a. The court began by addressing what it perceived to be
the principal focus of petitioner's attack: the Commission's approval of
NEPCO's tariff amendment permitting wholesale customers like petitioner
to terminate their long-term contracts early, subject to the payment of
a CTC. First, the court rejected petitioner's contention that in approving
the CTC the Commission violated its Order No. 888 stranded-cost regulations.
The Commission had found that those regulations did not apply to NEPCO's
filings. The court affirmed the Commission's interpretation of the regulations
and went on to observe, as did the Commission, that there was a separate
(although parallel) justification for stranded-cost recovery specifically
recognized by Order No. 888:
[Petitioner] as a requirements-contract customer of power furnished by New
England Power is being afforded an option to switch immediately to a competing
supplier, without the seven years' notice required by the contract. New
England Power Co., 83 FERC ¶ 61,174 at 61,722-23 (1998). In short,
there is a different reason for similar relief; and while Order No. 888
does not mandate the new tariff, neither does it forbid it. See Order No.
888, 61 Fed. Reg. at 21662 (reserving the possibility of stranded cost recovery
in other situations).
Pet. App. 10a.
Next, the court of appeals addressed petitioner's claim that the CTC was
nothing more than an effort to collect contract damages and therefore was
inconsistent with FERC's practice of deferring to the courts on matters
involving contract disputes. In rejecting that claim, the court of appeals
found that while the Commission precedent relied on by petitioner reflected
an unwillingness on the part of the Commission to resolve disputes over
the meaning of contract provisions, no such dispute was involved here, where
the Commission was merely approving, on a generic basis, a CTC for customers
who wished to terminate their contracts early. Pet. App. 11a.
The court of appeals also found no merit to petitioner's claims that the
Commission was required to reject NEPCO's proposed CTC on the basis of the
Mobile-Sierra and filed rate doctrines. As to the Mobile-Sierra doctrine,
the court took the view that, by permitting its non-affiliated customers
to terminate their contracts early subject to the payment of a CTC, NEPCO
could be viewed as having modified the contract. But the court went on to
note that
from [petitioner's] vantage, the option merely gives it something that it
did not have before; it remained free to insist that New England Power continue
to supply power under the contract until expiration. The termination charge
is certainly a detriment, but, absent a showing that its formula is any
worse than contract damages, it merely spells out what would have been the
law's remedy if [petitioner] had no option but simply breached the existing
contract.
Pet. App. 12a.
Generally, the filed rate doctrine works to prohibit retroactive increases
for tariffed services. See Arkansas La. Gas Co. v. Hall, 453 U.S. 571, 577-578
(1981). Applying that formulation of the doctrine, the court of appeals
found no error in the Commission's approval of the CTC tariff amendment.
The court reasoned that, as the tariff amendment did not require petitioner
to pay more for past purchases, there was no retroactive increase for tariffed
services. Instead, the tariff amendment merely gave petitioner an option
it did not have before to cancel future purchases on short notice, subject
to the payment of termination charges. Pet. App. 12a-13a.
The court of appeals also rejected petitioner's contentions that NEPCO's
proposed CTC was unduly discriminatory because it differed from the CTC
that NEPCO had negotiated by settlement with its affiliates and that a full
evidentiary hearing was warranted on this issue. Pet. App. 15a. In rejecting
that argument, the court observed that differential treatment does not necessarily
amount to undue preference where the difference in treatment can be explained
in an acceptable manner. Ibid. Here, the court affirmed the Commission's
determination that differential treatment was acceptable because petitioner
had passed up the opportunity to settle on the same terms as NEPCO's affiliates.
Id. at 16a-17a. Moreover, as petitioner's request for a hearing had been
ruled by the Commission to be untimely and unsupported, and petitioner had
not rebutted those rulings, the court of appeals found no merit to petitioner's
claim that it was entitled to a hearing. Id. at 16a.
This left petitioner's claims that the wholesale standard offer rates, which
were offered to NEPCO's affiliates under the terms of the settlement but
not to petitioner, were unduly discriminatory, and when coupled with the
CTC, were anticompetitive. The court of appeals held that it was not discriminatory
for NEPCO to limit its standard offer rates to its affiliates, because only
its affiliates, and not petitioner, were required by state regulators to
provide corresponding retail standard offer rates to their own customers.
Pet. App. 17a-18a. The court held that the fact that petitioner, as a municipal
system, was under no obligation to provide such service distinguished petitioner
from NEPCO's affiliates and sufficiently justified differential treatment.
Id. at 18a. As to petitioner's claims of anticompetitive effects, the court
found that petitioner had forfeited any argument on that issue because it
had done little more than make conclusory allegations and had "virtually
abdicated its responsibility to brief the issue to us." Id. at 21a.
ARGUMENT
The decision of the court of appeals is correct and does not conflict with
any decision of this Court or any other court of appeals. Further review
by this Court is therefore not warranted.
1. Petitioner contends that the court of appeals and FERC misapplied agency
regulations and agency and judicial precedent to the facts of this case.
The misapplication of settled law to particular facts, however, does not
warrant this Court's review. In any event, the court of appeals properly
evaluated and rejected petitioner's several claims.
a. Petitioner's contention that the court of appeals misread the Commission's
Order No. 888 regulations regarding the recovery of stranded costs, and
thereby created a major uncertainty requiring the Court's review (Pet. 13-16),
has no basis. As the Commission made plain in issuing Order No. 888, the
stranded-cost regulations promulgated by that order were not to serve as
the exclusive means for a utility to recover stranded costs.7 As the court
of appeals correctly observed, "the restrictions in Order No. 888 are
no more than conditions on stranded cost recovery under that order and do
not preclude the Commission from allowing tariffs that permit somewhat similar
recovery whenever a customer purports to disregard an existing contractual
obligation." Pet. App. 10a-11a (emphasis added). Cf. Transmission Access
Policy Study Group v. FERC, 2000 WL 762706, at *23-*25 (recognizing that
FERC's Order No. 888 stranded-cost recovery regulations were created to
deal with stranded costs incurred by FERC's regulation requiring open-access
transmission service). Thus there is no basis for petitioner's claim that
NEPCO's proposed CTC should have been rejected because it did not meet the
requirements of those regulations,8 and there is no "uncertainty,"
as petitioner claims (Pet. 16), in the recovery of stranded costs. In any
event, should such uncertainty arise, it can be addressed in the first instance
through administrative proceedings and, if necessary, appellate review,
and does not now warrant this Court's attention.
b. Nor was there any misapplication of breach-of- contract law, as petitioner
claims (Pet. 17-18). As the court of appeals properly characterized the
matter, there is no breach of contract at issue in this case. Pet. Ap. 11a.
The Commission neither interpreted petitioner's contract with NEPCO nor
determined whether petitioner breached its contract with NEPCO. Rather,
at issue was a general tariff amendment providing an option for customers
bound by existing contracts to terminate their long-term obligations by
paying a CTC. The Commission's decision does not address the situation of
customers breaching their contracts. Thus, this case presents no significant
question of contract law, much less "an irreconcilable conflict"
with the jurisdiction of courts adjudicating breach-of-contract claims,
as petitioner argues.
2. Petitioner argues (Pet. 18-24) that the court of appeals erroneously
applied this Court's decisions to the facts of the case. In particular,
petitioner claims that the court of appeals misapplied the Mobile-Sierra
and filed rate doctrines in reviewing and ultimately upholding the Commission's
acceptance of tariff amendments permitting the imposition of a CTC. Again,
petitioner claims no more than a misapplication of settled legal principles
to the facts of this case. In any event, petitioner's claims of error are
mistaken.
a. Under the Mobile-Sierra doctrine, the Commission may not approve filed-for
changes to a contract that are inconsistent with existing contractual obligations,
absent a finding that such changes are in the public interest. The court
of appeals held that FERC's approval of NEPCO's tariff amendment giving
customers something they did not have before, i.e., the ability to terminate
long-term contracts early subject to payment of a CTC, triggered no Mobile-Sierra
concerns. Pet. App. 12a. Regardless of the tariff amendment, petitioner
remained free to continue to require NEPCO to supply it with power under
the terms of its existing contract until, in the normal course, the contract
expired by its terms. Because the tariff amendment did not impose any new
contractual obligation on petitioner or alter any existing contractual obligation
to petitioner's detriment, the court of appeals rightly confirmed that petitioner
could have no objection to the tariff amendment under the Mobile-Sierra
doctrine.9
b. The filed rate doctrine "forbids a regulated entity to charge rates
for its services other than those properly filed with the appropriate regulatory
authority." Arkansas La. Gas Co. v. Hall, 453 U.S. 571, 577 (1981).
Below, petitioner argued that the obligation to pay a CTC under the revised
tariff provisions approved by FERC was retroactive because it was imposed
after petitioner had ceased making purchases from NEPCO. Pet. App. 13a.
As the court of appeals observed, however, the tariff change governed only
future purchases of power or failures to purchase power from NEPCO, and
not rates for purchases made by petitioner in the past. Ibid. Because the
court of appeals was manifestly correct on this point-the CTC being triggered
by the wholesale customer's exercise of a newly-created option -there was
no misapplication of the filed rate doctrine.
c. Petitioner's final claim (Pet. 24-27) is that FERC improperly declined
to hold an evidentiary hearing. As the Commission found, and the court of
appeals affirmed, petitioner's proffer simply did not support its claims
of undue discrimination. See Pet. App. 16a-19a. Under those circumstances,
it was no abuse of discretion for the Commission to rely on the evidence
submitted and to resolve the issues on the written record and without further
trial-type evidentiary hearings. See United States v. Florida E. Coast Ry.,
410 U.S. 224, 241 (1973); Moreau v. FERC, 982 F.2d 556, 568 (D.C. Cir. 1993);
American Pub. Gas Ass'n v. FPC, 567 F.2d 1016, 1066 (D.C. Cir. 1977).
CONCLUSION
The petition for writ of certiorari should be denied.
Respectfully submitted.
SETH P. WAXMAN
Solicitor General
DOUGLAS W. SMITH
General Counsel
DENNIS LANE
Solicitor
JOHN H. CONWAY
Associate Solicitor
LARRY D. GASTEIGER
Attorney
Federal Energy Regulatory
Commission
AUGUST 2000
1 Order No. 888, Promoting Wholesale Competition Through Open Access Non-Discriminatory
Transmission Services by Public Utilities; Recovery of Stranded Costs by
Public Utilities and Transmitting Utilities, 61 Fed. Reg. 21,540 (1996),
clarified, 76 F.E.R.C. ¶¶ 61,009 and 61,347 (1996), modified,
Order No. 888-A, 62 Fed. Reg. 12,274 (1997), on reh'g, Order No. 888-B,
81 F.E.R.C. ¶ 61,248 (1997), on reh'g, Order No. 888-C, 82 F.E.R.C.
¶ 61,046 (1998), aff'd in part and remanded in part sub nom. Transmission
Access Policy Study Group v. FERC, No. 97-1715, 2000 WL 762706 (D.C. Cir.
June 30, 2000).
2 Several States, including Massachusetts and Rhode Island, have acted within
their authority to regulate intrastate retail services to encourage electric
utility competition. They have, inter alia, adopted retail access programs
to require electric utilities within their borders to provide retail customers
a choice of electricity suppliers.
3 Under NEPCO's contracts with its affiliates, neither party could terminate
the long-term power contract without providing seven-years' advance notice
of termination. See Pet. App. 5a.
4 The standard offer rates were intended to provide a safeguard for retail
customers of the affiliates that did not or could not immediately take advantage
of the competitive sources of retail supply that were expected to develop.
The rates increased sharply over a brief period of time to induce customers
to migrate to the competitive market once they have had time to negotiate
with retailers that, as a result of federal and state efforts to provide
access to new sources of power, would now be able to compete to supply once-captive
customers. Pet. App. 17a-18a.
5 Petitioner had purchased power from NEPCO since 1983, under FERC-approved
agreements, for resale to petitioner's retail customers. See Town of Norwood
v. FERC, No. 99-2155, 2000 WL 822872, at *1 (1st Cir. June 29, 2000).
6 For a description of the history and disposition of that contract dispute,
see Town of Norwood v. New England Power Co., 202 F.3d 408 (1st Cir. 2000),
petition for cert. pending, No. 99-1913.
7 See Order No. 888, 61 Fed. Reg. 21,662 (1996) (noting that, in the case
of "voluntary restructuring," FERC "[is] willing to consider
case-specific proposals for dealing with stranded costs"); see also
Order No. 888-A, 62 Fed. Reg. 12,382 (1997) ("Order No. 888 does not
by its terms bar the recovery of costs that do not result from the use of
Commission-required transmission access (i.e., costs that result when a
departing customer does not use the former supplying utility's open-access
tariff). Utilities may, as before, seek recovery of such non-open-access-related
costs on a case-by-case basis in individual rate proceedings."); id.
at 12,406 ("Such costs are outside the scope of the rule [No. 888]
because such costs would not be stranded as a direct result of the new open
access.").
8 Petitioner wrongly suggests (Pet. 15-16) that NEPCO could not permissibly
amend its tariff to provide customers the option of terminating their long-term
contracts early by paying a CTC absent compliance with Order No. 888's stranded-cost
regulations. That contention overlooks FPA Section 205, 16 U.S.C. 824d,
under which public utilities subject to FERC's jurisdiction, such as NEPCO,
may file, and FERC may approve, lawful amendments to tariffs governing wholesale
power sales. As NEPCO's tariff amendment was precisely the type of filing
permitted by that provision, no additional authority, under Order No. 888
or any other rule, was required.
9 Petitioner argues (Pet. 22) that the court of appeals erred in holding
that the CTC merely gave petitioner an option to terminate that it had not
previously had. According to petitioner (Pet. 22), FERC did not allow the
CTC until May 15, 1998, almost a month after petitioner had terminated its
contract with NEPCO on April 22, 1998, and therefore subjected itself to
the CTC. NEPCO, however, had filed the CTC with FERC on March 18, 1998,
and it was accepted to be effective as of March 31, 1998. See Pet. App.
102a. Accordingly, at the time of the termination of petitioner's contract
with NEPCO, petitioner was already on notice of the CTC, and the CTC was
in fact made effective prior to the date of the termination.