No. 00-1025
In the Supreme Court of the United States
TOWN OF NORWOOD, MASSACHUSETTS, PETITIONER
v.
FEDERAL ENERGY REGULATORY COMMISSION, ET AL.
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT
BRIEF FOR THE
FEDERAL ENERGY REGULATORY COMMISSION
IN OPPOSITION
BARBARA D. UNDERWOOD
Acting Solicitor General
Counsel of Record
Department of Justice
Washington, D.C. 20530-0001
(202) 514-2217
KEVIN P. MADDEN
General Counsel
DENNIS LANE
Solicitor
LARRY D. GASTEIGER
Attorney
Federal Energy Regulatory
Commission
Washington, D.C. 20426
QUESTION PRESENTED
Whether petitioner's exercise of an option to extend a wholesale power contract
was effective where, although the underlying contract that contained the
option had been filed with the Federal Energy Regulatory Commission, petitioner's
notice of its exercise of the option was not filed with the Commission.
In the Supreme Court of the United States
No. 00-1025
TOWN OF NORWOOD, MASSACHUSETTS, PETITIONER
v.
FEDERAL ENERGY REGULATORY COMMISSION, ET AL.
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE FIRST CIRCUIT
BRIEF FOR THE
FEDERAL ENERGY REGULATORY COMMISSION
IN OPPOSITION
OPINIONS BELOW
The opinion of the court of appeals (Pet. App. 1a-13a) is reported at 217
F.3d 24. The order of the Federal Energy Regulatory Commission (Pet. App.
14a-23a) is reported at 87 F.E.R.C. ¶ 61,341.
JURISDICTION
The judgment of the court of appeals was entered on June 29, 2000. A petition
for rehearing was denied on August 25, 2000 (Pet. App. 24a-25a). On November
13, 2000, Justice Souter extended the time within which to file a petition
for a writ of certiorari to and including December 22, 2000, and the petition
was filed on that date. The jurisdiction of this Court is invoked under
28 U.S.C. 1254(1).
STATEMENT
1. Section 205(c) of the Federal Power Act (FPA), 16 U.S.C. 824d(c), requires
public electric utilities to file with the Federal Energy Regulatory Commission
(Commission or FERC) all rates and charges pertaining to sales of electric
power within the Commission's jurisdiction "and the classifications,
practices, and regulations affecting such rates and charges," as well
as all contracts that "affect or relate to such rates, charges, classifications,
and services." Changes to previously filed rates or contracts must
be submitted in accordance with Section 205(d) of the FPA, 16 U.S.C. 824d(d).
Those statutory provisions are consistent with the judicially developed
"filed rate doctrine," which generally forbids a utility from
charging rates other than those on file with the regulating agency at the
time the service is provided. See generally Arkansas La. Gas Co. (Arkla)
v. Hall, 453 U.S. 571, 577-578 & n.7 (1981).
2. Beginning in 1983, petitioner purchased wholesale electric power from
New England Power Company (NEPCO) for petitioner's municipal electric company.
Pet. App. 2a.1 NEPCO is a public utility subject to the Commission's jurisdiction
under the FPA. The contract between petitioner and NEPCO stated that NEPCO
would provide electric service to petitioner under NEPCO's FERC Tariff No.
1. Ibid. Tariff No. 1, in turn, provided that once NEPCO initiated service,
service would continue until terminated by either party's written notice
of termination, which had to be provided at least seven years in advance.
Id. at 15a. The contract fixed November 1, 1998 as the earliest date on
which either party could terminate the contract. Consistent with the tariff's
notice provision, the contract provided that petitioner and NEPCO could
not give notice of termination prior to November 1, 1991 (seven years before
the earliest possible termination date). Id. at 2a.
In 1989, petitioner and NEPCO amended their power contract to allow petitioner,
at its option, to postpone the earliest date at which either party could
give notice of termination by up to 20 years, in 10-year increments. Pet.
App. 3a, 15a. Petitioner could exercise its option by providing NEPCO written
notice one year before the date on which the extension would take effect.
Id. at 15a-16a. NEPCO filed the contract amendment with the Commission,
and the Commission accepted it on March 29, 1989. Id. at 16a.
On July 25, 1990, petitioner gave notice that it was extending the contract
for the first 10-year increment. Petitioner's letter to NEPCO stated:
The Town of Norwood, Massachusetts hereby gives notice to New England Power
Company that it extends the date by which either [NEPCO] or Norwood could
give notice of intent to terminate service from the present date of November
1, 1991, contained in the Power Contract between [NEPCO] and Norwood dated
April 11, 1983, to November 1, 2001. The effect of this is that the Power
Contract between [NEPCO] and Norwood would be extended for 10 years to midnight,
October 31, 2008 (Article III, Paragraph A).
This notice is given pursuant to Article III of the contract of April 11,
1983, as amended January 11, 1989.
Pet. App. 16a.
Beginning in 1996, NEPCO made a series of filings with the Commission in
which it sought authority to restructure NEPCO and its services in preparation
for competition among power suppliers. Among other things, NEPCO sought
authority to divest some of its power-generating facilities. Petitioner
objected to the proposed divestiture. Pet. 5; Pet. App. 3a-4a. After the
Commission approved NEPCO's request, petitioner notified NEPCO on March
4, 1998 that it intended to terminate its contract with NEPCO as of April
1, 1998 -thus giving NEPCO less than one month's notice of termination.
Pet. App. 3a-4a, 17a n.9. Petitioner further informed NEPCO that it was
withdrawing its notice of July 25, 1990, which had extended the contract.
Id. at 17a n.9.
On March 18, 1998, NEPCO responded by filing an amendment to its FERC Tariff
No. 1 under which customers were given the option of terminating service
on only 30 days' notice, subject to a charge that would compensate NEPCO
for the early termination. Pet. App. 4a & n.1, 16a. NEPCO represented
that, if approved by the Commission, the new option would allow petitioner
to terminate its existing service effective on April 1, 1998, rather than
on November 1, 2008 (the earliest date for termination under the 1983 contract
as extended by petitioner in 1990). Id. at 17a-18a. The Commission rejected
petitioner's objections to the amount of NEPCO's early-termination charge,
and approved NEPCO's tariff amendment. New England Power Co., 83 F.E.R.C.
¶ 61,174, reh'g denied, 84 F.E.R.C. ¶ 61,175 (1998), aff'd, Town
of Norwood v. FERC, 202 F.3d 392 (1st Cir.), cert. denied, 121 S. Ct. 57
(2000).
3. In April 1999, petitioner requested that the Commission issue a declaratory
order that petitioner's contract with NEPCO had terminated on October 31,
1998, so that NEPCO could not assess contract termination charges for any
period after that date. Pet. App. 4a. The Commission rejected petitioner's
request. Id. at 14a-23a.
The Commission found that petitioner's letter of July 25, 1990, validly
extended the power contract until October 31, 2008. Pet. App. 21a-23a. In
so ruling, the Commission rejected petitioner's claim that the contract
extension was ineffective because NEPCO did not file petitioner's letter
of July 25, 1990, with the Commission. The Commission explained that it
had approved the 1989 amendment that allowed petitioner to extend the termination
date, and petitioner's exercise of that already-approved option did not
require further Commission approval. Id. at 22a-23a.
4. The court of appeals denied petitioner's petition for review. Pet. App.
1a-13a. The court found it "crystal clear" that under the terms
of the 1989 amendment, petitioner's letter of July 25, 1990, did extend
the power contract through October 31, 2008, at the earliest. Id. at 6a.
The court of appeals also rejected petitioner's contention that NEPCO's
failure to file the July 25, 1990, letter with the Commission rendered the
contract extension ineffective. Pet. App. 7a-11a. The court found nothing
in Section 205 of the FPA (16 U.S.C. 824d) or in FERC's regulations that
required NEPCO to file the letter. Section 205 and the regulations both
require that public utilities file rates and charges, as well as contracts
that affect rates and charges. Pet. App. 8a; see 16 U.S.C. 824d(c) and (d);
18 C.F.R. 35.2. Because the contract extension did not change rates or charges,
the issue was whether petitioner's July 25, 1990, letter invoking the contract-extension
option was itself a contract (or contract amendment) that had to be filed.
Pet. App. 9a. Noting that "it would be a linguistic stretch" to
deem petitioner's notice a "contract," the court of appeals held
that the issue was, in any event, resolved by the Commission's reasonable
determination that neither the FPA nor Commission regulations require electric
utilities to file a notice of election that is authorized under a previously
filed contract. Id. at 9a & n.3.
The court of appeals found no inconsistency between the Commission's holding
that the contract extension did not have to be filed and this Court's decision
in Arkla, supra. Pet. App. 10a. That case involved a claim that Arkla's
alleged purchase of higher-cost gas from the United States triggered the
"most-favored nations clause" in Arkla's contract with private
gas suppliers, so that the rate due to the private suppliers under the contract
should have been the price Arkla was paying the United States, rather than
the lower rate specified in the contract. See 453 U.S. at 573-576. This
Court held that the rate schedule in Arkla's filed contract prevailed over
Arkla's contingent promise to pay an unspecified higher rate under the most-favored
nations clause. Id. at 579-584. The Court stressed that regulators' acceptance
of Arkla's contract with the private suppliers did not constitute pre-approval
of particular rates that might be calculated in the future under the most-favored
nations clause. In fact, it was unclear whether a rate increase based on
the most-favored nations clause would have been approved. Id. at 580-582
& n.11.
The court of appeals distinguished Arkla on the basis that, in this case,
"there is no effort by anyone to charge or obtain a rate different
than that on file with the Commission. And, as for duration, all of the
contract terms being given effect by the FERC orders under review are on
file with the Commission." Pet. App. 11a. The court of appeals concluded
that "[t]his is a situation very different from Arkla where, based
on a 'favored nations' clause containing no specific rate, the producer
sought-over the Commission's expressed objection- to recover from the purchasing
utility a rate for natural gas higher than the specific rate on file with
the Commission." Ibid.
Finally, the court of appeals rejected petitioner's arguments (not renewed
in this Court) that the July 1990 extension of the power contract was invalid
under the Mobile-Sierra doctrine,2 that the Commission lacked authority
to interpret the July 1990 letter, and that the Commission improperly denied
petitioner an opportunity to file an additional pleading. Pet. App. 11a-13a.
ARGUMENT
The decision of the court of appeals is correct and does not conflict with
any decision of this Court or any other court of appeals. Further review
by this Court therefore is not warranted.
1. Petitioner argues (Pet. 8-14) that the court of appeals' decision is
inconsistent with the "teachings" (Pet. 9) of Arkla and AT&T
Co. v. Central Office Telephone, Inc., 524 U.S. 214 (1998). There is no
conflict with either decision.
As the court of appeals explained, Arkla established that a properly filed
rate is effective until it is replaced by another properly filed rate (or
the rate is properly withdrawn), even if the utility's contracts arguably
require the utility to replace the filed rate with a new, but unspecified,
rate. See 453 U.S. at 578-582.3 Here, however, the Commission approved petitioner's
option to extend the contract termination date in 10-year increments when
it accepted the 1989 contract amendment. When petitioner exercised that
option in July 1990, it was simply availing itself of a term that had been
offered by NEPCO and already approved by the Commission, and no further
Commission approval was required. See Pet. App. 22a ("Because the July
25, 1990, letter was [petitioner's] exercise of a preapproved option, it
thus was not required to be filed with the Commission.").
Petitioner further claims (Pet. 12-14, 15) that "[t]he real basis for
the court of appeals' holding appears to be that the option at issue deals
with contract length rather than rates" and, so construed, the decision
below conflicts with Central Office Telephone, supra. In Central Office
Telephone, the Court rejected the argument that the filed rate doctrine,
as applied under the Communications Act of 1934 (ch. 652, 48 Stat. 1064,
47 U.S.C. 151 et seq.), applies only to rates themselves. Rather, the Court
held, the doctrine forbids a utility from providing its customer "discriminatory
privileges" that are inconsistent with the terms on file with the regulating
agency. 524 U.S. at 223-224. That holding has no application here. Contrary
to petitioner's mischaracterization of the decision below, the court of
appeals fully recognized the breadth of the filed rate doctrine. The court
of appeals simply (and correctly) concluded that "giving effect to
the [July 25, 1990] notice does not circumvent any filing requirement or
contradict any extant filing" relating to the power contract between
petitioner and NEPCO. Pet. App. 11a. That is so because "all of the
contract terms being given effect by the FERC orders under review are on
file with the Commission." Ibid. In short, the unremarkable and entirely
correct holding of the court of appeals was that the Commission's approval
of the 1989 contract amendment constituted approval of the optional contract
extension.
2. Petitioner further claims (Pet. 15-17) that, because NEPCO did not file
the letter extending the contract termination date, the duration of the
power contract between petitioner and NEPCO is no longer deducible from
materials on file with the Commission. That result, petitioner argues, fosters
uncertainty, allows "secret" agreements between utilities and
their customers, and "creates a significant breach in the filed rate
doctrine." Pet. 16.
Petitioner is mistaken. As an initial matter, petitioner's claim that the
Commission's files historically have revealed "precisely all of the
terms applicable [to a regulated sale of electric power] at a particular
time" (Pet. 15), is incorrect. As the court of appeals explained, there
always have been "gaps in what could be gleaned from Commission filings."
Pet. App. 9a-10a (citing Towns of Concord & Wellesley v. FERC, 844 F.2d
891 (1st Cir. 1988) (termination of a contract provision through an unfiled
letter), and Transwestern Pipeline Co. v. FERC, 897 F.2d 570, 577-579 (D.C.
Cir.) (inclusion of a rate formula rather than stated rates in a filed tariff),
cert. denied, 498 U.S. 952 (1990)).
In this case, moreover, the Commission's files have revealed at all times
what extension options are available to petitioner, and whether the contract
is in force. The files contain the original contract, the 1989 amendment,
and FERC Tariff No. 1, which collectively provide the relevant terms for
extending or terminating the contract. See Pet. App. 15a-16a. The absence
of any notice of termination of service in the file shows that the contract
is still in force.4 Thus, the Commission's files presently reveal both petitioner's
right to extend the contract in 10-year increments, and that the parties
did extend the contract beyond October 31, 1998. There is nothing "secret"
about the terms of the agreement between petitioner and NEPCO.
CONCLUSION
The petition for writ of certiorari should be denied.
Respectfully submitted.
BARBARA D. UNDERWOOD
Acting Solicitor General
KEVIN P. MADDEN
General Counsel
DENNIS LANE
Solicitor
LARRY D. GASTEIGER
Attorney
Federal Energy Regulatory
Commission
MARCH 2001
1 The 1983 contract and the history of petitioner's dispute with NEPCO are
described in Town of Norwood v. New England Power Co., 202 F.3d 408 (1st
Cir.), cert. denied, 121 S. Ct. 57 (2000), and Town of Norwood v. FERC,
202 F.3d 392 (1st Cir.), cert. denied, 121 S. Ct. 57 (2000).
2 The Mobile-Sierra doctrine prohibits a regulated utility from changing
the terms of a contract unilaterally, absent a Commission finding that the
existing term adversely affects the public interest. See FPC v. Sierra Pacific
Power Co., 350 U.S. 348, 353-355 (1956); United Gas Pipe Line Co. v. Mobile
Gas Serv. Corp., 350 U.S. 332, 343-345 (1956).
3 All but one of the lower court decisions on which petitioner relies (Pet.
11-12), which pre-date Arkla by 20 years or more, are to the same effect
as Arkla. The exception is Episcopal Theological Seminary v. FPC, 269 F.2d
228 (D.C. Cir.), cert. denied, 361 U.S. 895 (1959). That decision upheld
application of a Federal Power Commission regulation under which every rate
change was deemed to be a change in the rate schedule, which required re-filing.
Id. at 233-234. Episcopal Theological Seminary has no relevance to the FERC
ruling under review in this case.
4 Commission regulations require, for power contracts executed prior to
July 9, 1996, that the Commission be notified at least 60 days in advance
when a rate schedule on file is proposed to be canceled or is to terminate
by its own terms and no new rate schedule is to be filed in its place. 18
C.F.R. 35.15(a) and (b). July 9, 1996 was the effective date of Commission
Order No. 888, in which the Commission took steps to facilitate the development
of a competitive wholesale market for electric power. See generally Transmission
Access Policy Study Group v. FERC, 225 F.3d 667 (D.C. Cir. 2000), cert.
granted sub. nom. New York v. FERC, No. 00-568 and Enron Power Marketing,
Inc. v. FERC, No. 00-809 (Feb. 26, 2001).