No. 00-1056
In the Supreme Court of the United States
SOUTHWEST MARINE, INC., PETITIONER
v.
ROBERT B. PIRIE, JR.,
ACTING SECRETARY OF THE NAVY
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
BRIEF FOR THE RESPONDENT IN OPPOSITION
BARBARA D. UNDERWOOD
Acting Solicitor General
Counsel of Record
STUART SCHIFFER
Acting Assistant Attorney General
WILLIAM KANTER
WILLIAM G. COLE
Attorneys
Department of Justice
Washington, D.C. 20530-0001
(202) 514-2217
QUESTIONS PRESENTED
1. Whether the district court had jurisdiction to decide a government appeal
from a decision of the Armed Services Board of Contract Appeals regarding
a maritime contract.
2. Whether the court of appeals correctly held that the Navy may recoup
overpayments from a contractor due to a reduction in contract costs that
occurred two years after the contractor's bankruptcy discharge.
In the Supreme Court of the United States
No. 00-1056
SOUTHWEST MARINE, INC., PETITIONER
v.
ROBERT B. PIRIE, JR.,
ACTING SECRETARY OF THE NAVY
ON PETITION FOR A WRIT OF CERTIORARI
TO THE UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
BRIEF FOR THE RESPONDENT IN OPPOSITION
OPINIONS BELOW
The opinion of the United States Court of Appeals for the Ninth Circuit
(Pet. App. 1a-30a) is reported at 217 F.3d 1128. An opinion of the district court (Pet. App. 33a-49a) dated
October 7, 1998 and titled "Third Amended Order" is unreported.
The "Second Amended Order," dated October 1, 1998, from which
the appeal was taken to the Ninth Circuit, is unreported.1 The order of
the United States Court of Appeals for the Federal Circuit transferring
the case to the district court (Pet. App. 50a-59a) is reported at 120 F.3d
1249.
JURISDICTION
The judgment of the Ninth Circuit was filed on July 10, 2000. A petition
for rehearing was denied on September 25, 2000 (Pet. App. 31a-32a). The
petition for a writ of certiorari was filed on December 20, 2000. The jurisdiction
of this Court is invoked under 28 U.S.C. 1254(1).
STATEMENT
1. The Contract Disputes Act of 1978 (CDA), 41 U.S.C. 601 et seq., governs
disputes between the federal government and private contractors. Unless
otherwise specified, the CDA applies to any government procurement contract.
41 U.S.C. 602(a). However, the CDA provides that appeals arising out of
maritime contracts are governed by the Suits in Admiralty Act (SAA), 46
U.S.C. app. 741 et seq., and the Public Vessels Act (PVA), 46 U.S.C. app.
781 et seq., "to the extent that those [acts] are not inconsistent
with [the CDA]." 41 U.S.C. 603, 607(g)(1).
2. In 1985, Northwest Marine Iron Works (NMIW) entered into a contract with
the Navy to repair the U.S.S. Duluth. The work was completed and the ship
delivered to the Navy in 1986. The contract contained a cost-plus arrangement under which the Navy reimbursed NMIW for its actual
allowable costs, adjusted under a contractually defined formula limited
by a ceiling price. Under such an arrangement, the price for the repair
work is not determined at the time the contract is entered into, but rather
is calculated once the final cost is known. Pet. App. 8a-9a.
Before computation of the final price, progress payments were made to NMIW,
subject to standard clauses allowing for adjustment for overpayments and
a Credits Provision Clause that reduced the amounts chargeable to the Navy
in the event of a reduction in contractor costs.2 After delivery of the
U.S.S. Duluth to the Navy in June 1986, the contract remained open to resolve
several outstanding matters including determination of the final contract
price. Pet. App. 9a.
3. On October 29, 1986, NMIW filed a Chapter 11 petition in federal bankruptcy
court, which approved a reorganization plan for NMIW on March 20, 1987.3
In April 1987, NMIW submitted forms to the Navy identifying final costs
of $25,093,862 on the U.S.S. Duluth contract. On December 21, 1988, the
Navy agreed to settle NMIW's claims; on April 3, 1989, the Navy's contracting
officer executed a contract modification increasing the ceiling price to
$23,295,752.4 Subsequently, NMIW submitted a bill to the Navy for $2,811,077-the
difference between the new ceiling price and all prior progress payments.
Pet. App. 10a. On April 6, 1989, the Navy's contracting officer approved
the invoice, and the bill was paid shortly thereafter. Id. at 37a.
4. On February 23, 1989, after the NMIW submitted its final costs but before
the Navy contracting officer's approval, petitioner conditionally agreed
to purchase NMIW, dependent upon NMIW's receiving specific debt concessions
from its creditors. At this time, the Navy was not aware of these terms.
Pet. App. 37a. Petitioner's purchase of NMIW was completed on April 17,
1989. Three days later, the bankruptcy court issued a Chapter 11 Final Report
memorializing the concessions that the creditors agreed to. Id. at 10a-11a,
37a.
The following day, April 21, the Navy informed NMIW that it had learned
that at least one of NMIW's creditors had agreed to forgive some indebtedness.
The Navy indicated that, as a result, it was considering a recoupment action
for amounts it had paid to NMIW for which the contractor was no longer obliged
to pay. Pet. App. 11a. On April 26, NMIW responded that it was unaware of
any contract provision that would allow recovery of the Navy's prior payments.
Id. at 37a. Over the next five years, as the parties disputed these issues,
additional Navy audits showed that NMIW's costs under the U.S.S. Duluth
contract had decreased due to debt concessions by NMIW's creditors. The
Navy's contracting officer issued a final decision, finding that the Navy
had overpaid NMIW $2,161,287 and demanding repayment under three contract
provisions: the Progress Payments Clause, the Incentive Price Revision Clause,
and the Credits Provision Clause. Id. at 11a, 38a.
5. Pursuant to the CDA, petitioner appealed the decision to the Armed Services
Board of Contract Appeals (ASBCA). On October 11, 1996, the ASBCA ruled
in favor of petitioner, holding that the Navy was not entitled to recover
contract costs based on forgiveness of debts by NMIW's creditors subsequent
to NMIW's bankruptcy discharge. Pet. App. 11a-12a, 38a-39a.
6. On June 19, 1998, the Navy appealed the ASBCA decision to the United
States Court of Appeals for the Federal Circuit. That court ruled that it
lacked jurisdiction over the appeal since "there is no dispute that
this contract is wholly maritime." Pet. App. 52a (citing Southwest
Marine of San Francisco, Inc. v. United States (San Francisco), 896 F.2d
532 (Fed Cir. 1990)). Rather, the court held that the suit should have been
filed in district court. Pet. App. 58a.
The Federal Circuit also rejected petitioner's contention that any suit
filed in district court would have been time-barred under the SAA, and that
transfer therefore would be inappropriate. Pet. App. 53a-58a. Because the
CDA states that appeals arising out of maritime contracts are governed by
the SAA only to the extent that the SAA is not inconsistent with the CDA,
the court held that the SAA's two-year statute of limitations was inconsistent
with the CDA's provision that an aggrieved party must present its claim
to the contracting officer within six years of the accrual of its claim.
Id. at 56a-58a. Citing Crown Coat Front Co. v. United States, 386 U.S. 503
(1967), the court rejected petitioner's reliance on McMahon v. United States,
342 U.S. 25 (1951), in which this Court held that the SAA's limitations
period is not tolled while a claimant pursues available administrative remedies:
In [Crown Coat], the Court distinguished McMahon from cases that involve
the application of a contract disputes clause. Discussing the application
of the Tucker Act, the Court stated that "in disputes clause cases,
however, final administrative action, which the claimant must await, may
occur more than six years after the completion of a contract. When it does,
the claimant would be time-barred if the six-year period is measured from
the date of final performance." Id. at 517-18. The Court held that
when a claim arises under a contract and is subject to an administrative
determination pursuant to a disputes clause, the right to bring a civil
action does not accrue until an administrative determination is rendered.
Pet. App. 57a. The court noted that petitioner and the Navy had engaged
in negotiations for several years before a claim was submitted to the contracting
officer, who subsequently decided in favor of the Navy. The court observed
that, as a prevailing party, the Navy obviously would not have filed a civil
action at that time. Noting that the appeal to the ASBCA took over two years
to resolve, the court concluded that
[i]f * * * the Suits in Admiralty Act's two-year statute of limitations
accrues at the time a dispute arises, a party receiving an adverse decision
would almost always lose the opportunity to file a civil action while the
case was wending its way through the required administrative process. Application
of the limitations period in this manner would clearly be inconsistent with
the Contract Disputes Act and its procedures allowing for and governing
review of ASBCA decisions.
Id. at 57a-58a.
Accordingly, The Federal Circuit transferred the case, pursuant to 28 U.S.C.
1631, to the court in which it should have been filed, the United States
District Court for the Southern District of California. Pet. App. 58a-59a.
7. The district court ruled that it did possess jurisdiction under the CDA.
The court rejected petitioner's argument that, because the San Francisco
court noted that, in enacting the CDA, Congress "assured that no change
was made in the existing appellate path of disputes involving maritime contracts,"
896 F.2d at 534, the pre-CDA rule that agencies could not appeal adverse
board decisions remains valid with respect to maritime matters. Rather,
the district court held, the CDA does grant the government the right to
appeal board decisions even in maritime cases. Pet. App. 41a-43a.
Turning to the merits, the district court concluded that the ASBCA erred
in determining that the Navy's right to recover was barred by operation
of bankruptcy law. The court concluded that the ASBCA failed to note that
the Navy's effort to recover costs related to the voluntary post-petition
activities of NMIW's creditors, rather than NMIW's pre-petition debts that
were discharged in bankruptcy. Because "the Navy's recovery efforts
are not directed to the involuntary bar on debt collection raised by operation
of bankruptcy law," the court held that "as a matter of law, the
ASBCA erred when it determined that the bankruptcy discharge precluded the
Navy from seeking reimbursement for overpayment." Pet. App. 47a. The
court further held that the Navy was entitled to reimbursement under the
contract's Incentive Price Revision Clause and Credits Provision Clause.
Id. at 48a. Accordingly, the court reversed the decision of the ASBCA, and
remanded the matter to the ASBCA5 for a determination on the merits of quantum.
Ibid.
8. The Ninth Circuit affirmed the judgment of the district court. Because
the San Francisco court's "use of the phrase 'appellate path' was a
reference to jurisdiction, not the substantive question of whether a party
enjoys the right of appeal," the court of appeals agreed with the district
court that the Navy may appeal ASBCA decisions on maritime contracts. Pet.
App. 19a-20a. Noting that the CDA trumps the SAA where the two conflict,
the court concluded that because the CDA granted the Navy the right to appeal
adverse decisions, it was "irrelevant that pre-CDA law did not provide
for appeals by the government" in maritime matters. Id. at 22a.
Regarding the merits, the Ninth Circuit determined that
[t]he record clearly showed that the claimed reduction in Duluth contract
costs was based not on NMIW's bankruptcy discharge or the debenture holders'
inability to collect their pre-confirmation claims, but rather on the debenture
holders' subsequent decisions, some two years after the plan confirmation,
to compromise their post-confirmation claims-the debentures-as part of the
NMIW/ Southwest merger. Thus, the proper analysis must focus upon what effect,
if any, bankruptcy law provisions have upon post-confirmation acts which
compromise post-confirmation claims.
Pet. App. 27a-28a. The court observed that a bankruptcy plan binds pre-confirmation
creditors but not post-confirmation creditors. Therefore, because the Navy's
claim for recoupment of overpayment "arose out of the debenture holder's
post-confirmation decisions to compromise their post-confirmation claims, it was error for the ASBCA
to equate the debentures with the debenture holder's pre-confirmation claims."
Id. at 29a. Rather, "the correct focus should have been upon how the
debenture holders' voluntary relinquishment of their rights affected NMIW's
claim for costs on the Duluth project, a question wholly distinct from the
operation of the bankruptcy discharge." Ibid. As an application of
"straightforward government contracting law," the court concluded,
the Navy's right to recoupment was "clear" under the Credits Provision
Clause. Ibid. Accordingly, the court affirmed. Id. at 29a-30a.
ARGUMENT
The decisions of the Ninth Circuit and Federal Circuit in this case are
correct and do not conflict with any decision of this Court or of any other
court of appeals. Further review is not warranted.
1. Petitioner contends (Pet. 9-18) that jurisdiction did not properly lie
in the district court. Petitioner presents two alternative arguments: first
(Pet. 16-18), that the Federal Circuit should have accepted the appeal pursuant
to Section 607(g)(1) of the CDA; and second (Pet. 18), if the case was properly
in district court, then a governmental appeal was doubly barred by the pre-CDA
rule that the government could not appeal a decision of its own administrative
board and by the SAA's two-year statute of limitations. These arguments
are without merit. The courts below correctly interpreted the law governing
appeals from ASBCA decisions involving maritime contracts. The courts correctly
concluded that the CDA modified appellate rights without disturbing the
traditional jurisdictional allocation of maritime disputes to the district
courts. The courts' holdings are consistent with precedent and do not conflict
with any other decisions.
(a) Although the CDA and the Federal Courts Improvement Act of 1982 (FCIA),
which created the Federal Circuit, generally provide for appeals to the
Federal Circuit from decisions by agency boards of contract appeals, see
41 U.S.C. 607(g)(1); 28 U.S.C. 1295(a)(10), the CDA itself provides for
a different appeals process in maritime cases. Section 603 of the CDA provides
as follows:
Appeals under paragraph (g) of section 607 of this title and suits under
section 609 of this title, arising out of maritime contracts, shall be governed
by chapter 20 [the SAA] or 22 [the PVA] of title 46, Appendix, as applicable,
to the extent that those chapters are not inconsistent with this chapter.
41 U.S.C. 603.
Section 607(g)(1), in turn, provides:
(1) The decision of an agency board of contract appeals shall be final,
except that-
(A) a contractor may appeal such a decision to the United States Court of
Appeals for the Federal Circuit within one hundred twenty days after the
date of receipt of a copy of such decision, or
(B) the agency head, if he determines that an appeal should be taken, and
with the prior approval of the Attorney General, transmits the decision
of the board of contract appeals to the Court of Appeals for the Federal
Circuit for judicial review under section 1295 of title 28, within one hundred
and twenty days from the date of the agency's receipt of a copy of the board's
decision.
41 U.S.C. 607(g)(1).
Finally, the SAA provides that a proceeding in admiralty involving the United
States must be brought in a district court, 46 U.S.C. app. 742 (1994 &
Supp. IV 1998); 46 U.S.C. app. 782, and "may be brought only within
two years after the cause of action arises," 46 U.S.C. app. 745.
Any ambiguity regarding the proper court to hear appeals from ASBCA decisions
is resolved by the history of maritime jurisdiction and by the legislative
history of both the CDA and the FCIA. "Jurisdiction over matters arising
in admiralty, including maritime contracts, has traditionally been with
the federal district courts." San Francisco, 896 F.2d at 534; see also
Matson Navigation Co. v. United States, 284 U.S. 352, 356 (1932) ("[J]urisdiction
of maritime causes of action against the United States, arising out of the
operation of merchant vessels for it, is vested exclusively in the district
courts."). The Senate Report that accompanied the CDA stated that "the
current sole jurisdiction over all admiralty cases should remain in the
district courts where great expertise has been developed over the years
on such cases." S. Rep. No. 1118, 95th Cong., 2d Sess. 8 (1978).
Jurisdiction over matters arising in admiralty including maritime contracts
has vested exclusively with the Federal district courts since 1920 (See:
Suits in Admiralty Act, 46 U.S.C. 741-752, Matson Navigation Co. v. United
States * * *). As a result, the district courts have developed an expertise
in admiralty matters, which has resulted in a common body of procedural
and substantive law, applicable to private litigants and the United States
alike. Inclusion of maritime contracts within the bill would have created
an exception to the district courts' otherwise exclusive admiralty jurisdiction
and divided maritime contract disputes between the Court of Claims and district
courts depending upon whether the United States was a party plaintiff or
defendant. Admiralty matters sounding in contract involve issues and procedural
questions considered sufficiently unique so as to warrant the continued
maintenance of these actions within the exclusive jurisdiction of the district
courts.
Id. at 18.6
Similarly, the Senate Report that accompanied the FCIA reiterated Congress's
intention not to tamper with the district courts' jurisdiction over maritime
appeals:
Subsection (a)(10) of section 1295 of title 28 gives the Court of Appeals
for the Federal Circuit jurisdiction of an appeal from a final decision
of an agency board of contract appeals pursuant to section 8(g)(1) of the
Contract Disputes Act of 1978. No change is intended in the exclusive jurisdiction
of the federal district courts to hear appeals in government maritime contract
disputes, as provided in [41 U.S.C. 603].
S. Rep. No. 275, 97th Cong., 1st Sess. 21-22 (1982).
Therefore, the Federal Circuit correctly held, in accordance with its decision
in San Francisco, 896 F.2d at 534-535, that it lacked jurisdiction and that
the case should be transferred to the district court. Pet. App. 58a.
(b) Petitioner incorrectly alleges that if the CDA does not change the jurisdiction
of maritime appeals, then it must not change either (1) the rule prohibiting
the government from appealing decisions of its own administrative board
or (2) the applicable statute of limitations. In fact, the text, legislative
history and purposes of the CDA indicate that Congress intended those rules
to govern all contract disputes, including disputes over maritime contracts.
It is not surprising that Congress wanted the CDA to supersede the SAA in
some respects but not in others, given the CDA's intention both to "provide
alternate forums suitable to handle the different types of disputes"
and to "insure fair and equitable treatment to contractors and Government
agencies." S. Rep. No. 1118, supra, at 1. Petitioner offers no explanation
for why Congress would have wanted these SAA provisions to remain in force,
and indeed such a decision would have been illogical given the purposes
of the CDA.
Because the CDA significantly revised procedural aspects of government contract
law, Section 603 provides that appeals arising out of maritime contracts
are governed by the SAA and PVA only "to the extent that those [acts]
are not inconsistent with" the CDA. The legislative history quoted
above clearly indicates that Congress intended to preserve the pre-CDA appellate
path for reasons of efficiency and because the district courts had developed
expertise in admiralty matters. These concerns, while relevant to rules
that govern which court has jurisdiction, are not implicated by rules governing
(1) which parties may bring an appeal, or (2) how much time such parties
have in which to do so. Indeed, although Congress preserved the maritime
urisdiction of the district courts, there is no indication that Congress
intended to exempt maritime matters from potentially outcome-determinative
changes wrought by the CDA and by subsequent amendments to the Act. Section
607(g)(1)(B), permitting the government to appeal the decision of an agency
board of contract appeals, marked a watershed change in government contract
law. Neither the text, the legislative history, nor the purpose of the statute
provide any reason to suspect that Congress did not want to apply this provision
to maritime contracts. As the Senate Report stated:
The agency boards of contract appeals as they exist today, and as they would
be strengthened by this bill, function as quasi-judicial bodies. Their members serve as administrative
judges in an adversary-type proceeding, make findings of fact, and interpret
the law. Their decisions set the bulk of legal precedents in Government
contract law, and often involve substantial sums of money. In performing
this function they do not act as a representative of the agency, since the
agency is contesting the contractor's entitlement to relief. In this context,
the Government should have an equal right of judicial review, since it would
be an anomaly in the American judicial system for such a trial tribunals
[sic] to have the final authority on decisions that set important precedents
in procurement law.
S. Rep. No. 1118, supra, at 26. There is no indication either in the statutory
text or in the legislative history that Congress desired a different rule
to apply to appeals of maritime contract disputes. Indeed, such a change
would clearly have been "inconsistent with" the CDA. 41 U.S.C.
603. Accordingly, the Ninth Circuit correctly held that "[t]he Federal
Circuit's conclusion, that passage of the CDA did not change the way in
which maritime contract cases are to be brought, does not establish that
the substantive provisions of CDA, granting the Navy the right to appeal
adverse decisions, do not apply to maritime contract cases." Pet. App.
20a-21a.
Petitioner's view of the effect of the CDA on the government's right to
appeal is difficult to square with the CDA's text. Section 603 of the CDA,
which contains the cross-reference to the SAA that petitioner claims forbids
the government to appeal maritime decisions, applies to "[a]ppeals
under paragraph (g) of section 607." Yet Section 607(g) is the precise
provision of the CDA that creates the government's appellate rights. Thus,
petitioner's theory is that the cross-reference to the SAA in a section
that addresses "appeals under paragraph (g) of Section 607" destroys
the appellate rights enacted in that same paragraph. Petitioner's argument
is both illogical and implausible, especially because Congress could have
accomplished the result petitioner envisions simply by including the phrase
"except in maritime cases" within Section 607(g)(1)(B) of the
CDA.
Nor is there any indication that Congress intended
to exempt maritime contracts when it passed the 1994 amendment to the CDA,
Federal Acquisition Streamlining Act of 1994, Pub. L. No. 103-355, §
2351, 108 Stat. 3322, that set a six-year statute of limitations. The text
provides no such exemption, and the Federal Circuit correctly concluded
(Pet. App. 58a) that the legislative history provides no indication that
Congress wanted the amended CDA's statute of limitation to be trumped by
the SAA's shorter statute of limitations. Furthermore, the purposes of the
Act would not be served by creating such an illogical distinction.7
2. Petitioner argues (Pet. 18-20) that the decision of the court of appeals
to allow the Navy to recoup its overpayments contravenes bankruptcy law.
However, as the district court and the Ninth Circuit concluded, this case
is a straightforward government contract law case to which bankruptcy law
does not apply. Accordingly, petitioner's claim does not warrant further
review.
As the court of appeals held, the record clearly showed that the reduction
in the U.S.S. Duluth's contract costs was based not on NMIW's bankruptcy
discharge in 1987, but on its creditors' subsequent decisions, in 1989,
to forgive some of NMIW's indebtedness to induce petitioner to purchase
NMIW. Pet. App. 27a-28a. Since the creditors' 1989 forgiveness of NMIW's
debt was a question wholly distinct from the operation of the bankruptcy
discharge, petitioners err in arguing that this case affects bankruptcy
law at all.8
Under the Credits Provision Clause of the contract, NMIW was required to
credit back to the Navy any rebate, allowance or other credit related to
an allowable cost. Pet. App. 29a. The construction of this contract clause
by the court of appeals does not raise any question meriting this Court's
review. Moreover, the decision below correctly construed the contract. The
court of appeals properly found that the creditors' 1989 agreement to forgo
collection of certain claims against NMIW was such a rebate, allowance or
other credit. Ibid. Under the contract's cost-plus arrangement, the amount
paid the contractor by the government was determined by the contractor's
incurred costs. When debt concessions decreased those costs, the government's
obligation to the contractor decreased correspondingly. Therefore, the court
of appeals correctly held that the Navy was entitled to reimbursement.
CONCLUSION
The petition for writ of certiorari should be denied.
Respectfully submitted.
BARBARA D. UNDERWOOD
Acting Solicitor General
STUART SCHIFFER
Acting Assistant Attorney General
WILLIAM KANTER
WILLIAM G. COLE
Attorneys
MARCH 2001
1 The two decisions differ in that the final two sentences (and footnote
14) of the Second Amended Order, determining the amount of money to which
the Navy is entitled, were deleted in the Third Amended Order.
2 The Credits Provision Clause provides:
The applicable portion of any income, rebate, allowance, or other credit
relating to any allowable cost and received by or accruing to the contractor
shall be credited to the Government either as a cost reduction or by cash
refund.
Pet. App. 9a.
3 Petitioner inadvertently misstates this date as March 1997. Pet. 5.
4 The initial contract had a ceiling price of $15,966,613. Over the course
of the work, the parties executed over 200 change orders, many of which
altered the ceiling price. Pet. App. 9a n.4.
5 The October 1, 1998 Order (the Second Amended Order) from the district
court had ordered the remand but also had determined the sum for which petitioner
was liable. The October 7, 1998 Order (the Third Amended Order) deleted
the determination of the sum from the court's decision. The notice of appeal
to the Ninth Circuit by petitioner was filed on October 7, 1998 and was from the October
1, 1998 Order.
The legislative report defined very precisely that the current jurisdictions
for Maritime Contract claims is to be maintained and not changed by S. 3178.
Concern has been expressed by the Department of Defense that this position
should be included in the statute, thus [Section 603] has been added.
124 Cong. Rec. 36,267 (1978).
7 Even if the two-year statute of limitations were to apply to this case,
it would run, as the Federal Circuit determined, not from the inception
of the dispute but from the date of the ASBCA decision. Pet. App. 56a-58a.
In reaching this conclusion, the Federal Circuit correctly relied on Crown
Coat Front Co. v. United States, 386 U.S. 503 (1967), in which this Court
held that when a claim arises under a contract and is subject to an administrative
determination, the right to bring a civil action does not accrue until the
administrative determination is rendered. Pet. App. 57a. As the Federal
Circuit noted, a contrary conclusion would be illogical:
[T]he parties were in negotiations for several years before a claim was
submitted to the contracting officer. The contracting officer took additional
time to render a decision. It is worth reiterating that the contracting
officer sided with the secretary. Thus, the secretary could not have filed
a civil action at that juncture. Thereafter, the case was pending at the
ASBCA for over two years. If the court were to hold that the Suits in Admiralty
Act's two-year statute of limitations accrues at the time a dispute arises,
a party receiving an adverse decision would almost always lose the opportunity
to file a civil action while the case was wending its way through the required
administrative process. Application of the limitations period in this manner
would clearly be inconsistent with the Contract Disputes Act and its procedures
allowing for and governing review of ASBCA decisions.
Id. at 57a-58a.
8 Additionally, during NMIW's bankruptcy, the Navy was NMIW's debtor, not
a creditor, because the Navy owed money to NMIW for work on the U.S.S. Duluth.
Thus, its rights as a creditor could not have been affected by decisions
of the bankruptcy court in 1987. The Navy's only claim against NMIW arose
in 1989, when it paid NMIW $2.8 million, more than $2.2 million more than
the sum to which NMIW was entitled.