88.
Warranties
|
A. Express Warranties
Government contracts frequently contain express warranty
clauses.
The warranty clause, by its terms, provides the exclusive remedies
for
nonlatent defects or those not involving fraud or such gross
mistakes as
amount to fraud, by requiring the contractor to repair or replace
the
defective article or part, or, if the article or part was retained,
by
requiring the contractor to pay an amount which is equitable under
the
circumstances. See United States v. Franklin Steel Products, Inc.,
482
F.2d 400, 404 (9th Cir. 1973), cert. denied, 415 U.S. 918 (1974).
A
frequent defense asserted by contractors in such cases is that the
government's right of inspection before acceptance, under another
clause
included in such contracts, see 48 C.F.R. § 52.246-2 et seq.,
relieved the contractors of liability, since the government should
have
inspected, or it negligently inspected, the product or part.
However,
the inspection clause was added to give the government further
protection, not less. United States v. Aerodex, Inc., 469 F.2d 1003
(5th
Cir. 1972); United States v. Franklin Steel Products, supra.
Assuming,
arguendo, that the government had a duty to inspect, the warranty
clause
specifically provides that inspection and subsequent acceptance are
not
conclusive as to "latent defects, fraud, or such gross mistakes as
to
amount to fraud." Thus, latent defects, not discoverable by visual
inspection or the tests specified in the contract, would be the
basis
for relief in any event. See United States v. Franklin Steel
Products,
supra at 403.
B. Implied Warranties
1. Affirmative Actions Based on Implied Warranties.
Unless specifically forbidden from doing so by regulation or
by the
contract in question, the government may claim the benefits of
implied
warranties found in the Uniform Commercial Code (UCC). Although
federal
law applies to determine the rights and liabilities of parties to
a
government contract, the Uniform Commercial Code may serve as a
guide
for federal law in this area, at least to the extent that the
question
is not governed by the contract or by federal regulations. See
United
States v. Hext, supra; Everett Plywood & Door Corp. v. United
States,
419 F.2d 425 (Ct. Cl. 1969); United States v. Wegematic Corp., 360
F.2d
674 (2d Cir. 1966). The implied warranty of merchantability is
found at
section 2-314 of the UCC. The implied warranty of fitness for a
particular purpose is found at section 2-315. In a proper case, the
government may also recover incidental and consequential damages,
pursuant to section 2-715 of the UCC. It should be noted that the
implied warranties found in sections 2-314 and 2-315 will not apply
if,
prior to entering into the contract, there was an examination of
inspection of the goods by the buyer, unless the defects could not
have
been reasonably discovered at the time of the examination. U.C.C.
§
2-316.
2. Defenses to Allegations of Implied Warranties
A contractor may not defend or recover on an implied warranty
theory where the government expressly disclaims such warranties.
Webco
Lumber, Inc. v. United States, 677 F.2d 860 (Ct. Cl. 1982). This
issue
arises most often in contracts which contain an estimate of
quantities.
Where such estimates are clearly defined as estimates only and any
implied warranty is expressly disclaimed, the disclaimer will be
given
effect. Id.; Caffall Brothers Forest Products, Inc. v. United
States,
678 F.2d 1071 (Ct. Cl.), cert. denied, 459 U.S. 908 (1982). In
order to
prevail on a claim of breach of warranty, the plaintiff must
establish
that:
1. The government assured the plaintiff of the
existence of
a fact;
2. The government intended that the plaintiff be
relieved of
the duty to ascertain the existence of the fact for itself; and
3. The government's assurance of that fact proved
untrue.
See Kolar, Inc. v. United States, 650 F.2d 256 (Ct. Cl. 1981). All
implied warranty claims should be viewed in light of the accepted
proposition that the government does not normally guarantee the
success
of a contractor's operation. Id. For a warranty to exist, there
must be
either an affirmation of fact or a promise which relates to
performance
under the contract. American Ship Building Co. v. United States,
654
F.2d 75 (Ct. Cl. 1981). A requirement in a government contract that
performance be completed within a specified time is not a guarantee
that
performance can, in fact, be completed within that time. Id.
[cited in USAM 4-4.530]
| | |